Appellant / Complainant
Pardeep Kumar
Respondent
U.P. Avas Evam Vikas Parishad
₹93,25,574
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009072020 by Pardeep Kumar against U.P. Avas Evam Vikas Parishad before up_rera.
for delivery of Judgment/Order
The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.
Hearing
The Tribunal heard the arguments from both the appellant and respondent, after which the judgment was reserved for a later date.
Final Hearing
The Tribunal heard arguments regarding the appellant's grievance over the period of interest awarded for delay in possession and has reserved its judgment.
Hearing
The Tribunal directed the respondent to email a copy of their objections to the appellant and ordered both parties to file their respective replies on the e-portal and in the Registry before the next hearing on 24.11.2021.
Hearing
The Tribunal adjourned the appeal to 01.11.2021 due to the appellant's absence and directed the parties to exchange pleadings and file originals in the Registry prior to the next hearing.
For Order
The Tribunal directed the Registry to convert the defective appeal into a regular appeal and granted the respondent 10 days to file objections to the grounds of appeal.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 22.03.2021.
For Order
The court granted a joint request from the applicant and respondent's counsel to adjourn the matter, rescheduling the case for hearing on 05.03.2021.
Notice
The Tribunal directed the Registry to convert a defective appeal into a regular appeal and granted the appellant 10 days to file a reply to the respondent's objections.
Tribunal Order #0901126009072020-30-06-2022
The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 02.04.2015 to 28.02.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- In Person
Respondent Advocate(s)
- Vijay Pratap Singh Chauhan
Official RERA Tribunal Orders (1)
The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.