up_reraStatus: Completed
CASE ID: 0901126009072020

Appellant / Complainant

Pardeep Kumar

VS

Respondent

U.P. Avas Evam Vikas Parishad

Disputed Amount

93,25,574

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126009072020 by Pardeep Kumar against U.P. Avas Evam Vikas Parishad before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility Disputes
2
Stage 130/06/2022

for delivery of Judgment/Order

The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.

3
Stage 218/05/2022

Hearing

The Tribunal heard the arguments from both the appellant and respondent, after which the judgment was reserved for a later date.

4
Stage 324/11/2021

Final Hearing

The Tribunal heard arguments regarding the appellant's grievance over the period of interest awarded for delay in possession and has reserved its judgment.

5
Stage 401/11/2021

Hearing

The Tribunal directed the respondent to email a copy of their objections to the appellant and ordered both parties to file their respective replies on the e-portal and in the Registry before the next hearing on 24.11.2021.

6
Stage 504/10/2021

Hearing

The Tribunal adjourned the appeal to 01.11.2021 due to the appellant's absence and directed the parties to exchange pleadings and file originals in the Registry prior to the next hearing.

7
Stage 619/04/2021

Hearing

No text available.

8
Stage 722/03/2021

For Order

The Tribunal directed the Registry to convert the defective appeal into a regular appeal and granted the respondent 10 days to file objections to the grounds of appeal.

9
Stage 805/03/2021

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 22.03.2021.

10
Stage 909/02/2021

For Order

The court granted a joint request from the applicant and respondent's counsel to adjourn the matter, rescheduling the case for hearing on 05.03.2021.

11
Stage 1021/01/2021

Notice

The Tribunal directed the Registry to convert a defective appeal into a regular appeal and granted the appellant 10 days to file a reply to the respondent's objections.

12
Stage 1107/12/2020

Notice

No text available.

13
Stage 12Final Ruling Order

Tribunal Order #0901126009072020-30-06-2022

The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 02.04.2015 to 28.02.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • In Person

Respondent Advocate(s)

  • Vijay Pratap Singh Chauhan

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126009072020-30-06-2022

The Tribunal partially allowed the appeal, ruling that the project was delayed and modifying the Regulatory Authority's order to extend the interest period for delayed possession from 23.01.2017 back to 02.04.2015.