Appellant / Complainant
Shah Alam Khan
Respondent
Ccse Sahakari Awas Samiti Ltd.
ccse sahakari awas samiti ltd.
₹28,35,110
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126009012022 by Shah Alam Khan against Ccse Sahakari Awas Samiti Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by Shah Alam Khan, upholding the Regulatory Authority's order that no interest was due for delay in possession since the appellant had already taken possession and was using the unit.
Further Hearing
The Tribunal noted the submission of evidence regarding electricity and maintenance payments by the respondent and has reserved the judgment for further deliberation.
Hearing
The Tribunal directed the respondent to upload evidence of electricity and maintenance payments made by the appellant and ordered that the matter be heard the following day without further adjournment.
Hearing
The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work, rescheduling the hearing for 16.10.2023.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel via email and directed that future adjournment requests must be uploaded through the official e-portal folder.
Hearing
The Tribunal directed the appellant to clarify if the project is 'ongoing' based on previous OC/CC records and ordered the respondent to provide evidence regarding possession and whether the appellant currently occupies the unit.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and directed the respondent to provide soft copies of uploaded documents to the appellant within three days.
Further Order
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 20.03.2023.
Further Order
The Tribunal granted an adjournment requested by the counsels for both parties and rescheduled the appeal for hearing on 12.01.2023.
Further Order
The Tribunal directed the respondent to download the appellant's replication/rejoinder from the e-Portal and scheduled the appeal for a hearing on 14.12.2022.
Further Order
The Tribunal granted the Appellant's counsel one week to file a reply to the Respondent's objections and scheduled the next hearing for November 17, 2022.
Delay condonation
The Tribunal allowed the delay condonation application regarding a 17-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal has issued a routine procedural order to list the appeal on 16.09.2022.
Delay condonation
The Tribunal granted the applicant a final one-week extension to file a reply to the respondent's objections and scheduled the matter for hearing on 01.09.2022.
Delay condonation
The Tribunal granted the appellant two weeks to file a reply to the respondent's objection and scheduled the matter for hearing on August 10, 2022.
Delay condonation
The Tribunal granted the respondent two weeks to file objections regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 18, 2022.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and directed the respondent to upload their objections to the application for condonation of delay on the e-portal within one week.
Defect Removal
The Tribunal granted the appellant one week to remove registry defects and directed that notice be issued to the respondent for the next hearing on 10.05.2022.
Tribunal Order #0901126009012022-07-05-2024
The Appellate Tribunal dismissed the appeal filed by Shah Alam Khan, upholding the Regulatory Authority's order that no interest was due for delay in possession since the appellant had already taken possession and was using the unit.
Tribunal Order #0901126009012022-18-01-2024
The Tribunal directed the respondent to upload evidence of electricity and maintenance payments made by the appellant and ordered that the matter be heard the following day without further adjournment.
Tribunal Order #0901126009012022-06-07-2023
The Tribunal directed the appellant to clarify if the project is 'ongoing' based on previous OC/CC records and ordered the respondent to provide evidence regarding possession and whether the appellant currently occupies the unit.
Tribunal Order #0901126009012022-16-09-2022
The Tribunal allowed the delay condonation application regarding a 17-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by Shah Alam Khan, upholding the Regulatory Authority's order that no interest was due for delay in possession since the appellant had already taken possession and was using the unit. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by Shah Alam Khan, upholding the Regulatory Authority's order that no interest was due for delay in possession since the appellant had already taken possession and was using the unit.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Mohsin Khan
- Mohd Hayan Hasan
Respondent Advocate(s)
- Sanjay Sharma
Official RERA Tribunal Orders (4)
The Appellate Tribunal dismissed the appeal filed by Shah Alam Khan, upholding the Regulatory Authority's order that no interest was due for delay in possession since the appellant had already taken possession and was using the unit.
The Tribunal directed the respondent to upload evidence of electricity and maintenance payments made by the appellant and ordered that the matter be heard the following day without further adjournment.
The Tribunal directed the appellant to clarify if the project is 'ongoing' based on previous OC/CC records and ordered the respondent to provide evidence regarding possession and whether the appellant currently occupies the unit.
The Tribunal allowed the delay condonation application regarding a 17-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Need to research all rulings for ccse sahakari awas samiti ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.