up_reraStatus: Completed
CASE ID: 0901126008912024

Appellant / Complainant

Annapurna Pal

VS

Respondent

U.P. State Industrial Development Corporation Limited

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

33 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008912024 by Annapurna Pal against U.P. State Industrial Development Corporation Limited before up_rera.

2
Stage 124/02/2026

Hearing

The U.P. Real Estate Appellate Tribunal allowed the appellant's application to withdraw the appeal and subsequently dismissed the appeal as withdrawn.

3
Stage 202/02/2026

Hearing

The appeal is adjourned to 24.02.2026 due to a technical glitch causing server in-operationality.

4
Stage 319/12/2025

Hearing

The Tribunal granted a request for time to file an application for withdrawal of the appeal and adjourned the matter to 02.02.2026.

5
Stage 425/11/2025

Hearing

The Tribunal granted the respondent a final ten-day extension to file objections and scheduled the case for orders on 19.12.2025.

6
Stage 506/11/2025

Hearing

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for 25.11.2025.

7
Stage 613/10/2025

Hearing

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and allowed the appellant one week thereafter to file a rejoinder, with the matter listed for orders on 06.11.2025.

8
Stage 711/09/2025

Delay condonation

The Tribunal allowed the application for condonation of a 219-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.

9
Stage 827/08/2025

Delay condonation

The Tribunal granted the appellant's counsel time to argue the delay condonation application and scheduled the appeal for a hearing on 11.09.2025, noting that no further adjournments will be permitted.

10
Stage 913/08/2025

Delay condonation

The Tribunal directed the Registry to list this appeal along with related bunch matters before Bench No. 2 on 27.08.2025.

11
Stage 1029/07/2025

Delay condonation

The Tribunal ordered the appeal to be listed along with the record of Appeal No. 664 of 2023 on August 13, 2025.

12
Stage 1108/07/2025

Delay condonation

The court granted a 10-day extension to the respondent to file objections to the better affidavit and adjourned the appeal to July 29, 2025.

13
Stage 1216/05/2025

Delay condonation

At the request of the appellant's counsel, the tribunal has adjourned the matter and scheduled it for orders on July 8, 2025.

14
Stage 1323/04/2025

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 16.05.2025.

15
Stage 1425/03/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed the appellant to reply within one week thereafter, scheduling the matter for April 23, 2024.

16
Stage 1527/02/2025

Delay condonation

The Tribunal granted a request for adjournment and rescheduled the appeal to 25.03.2025, directing that pleadings be exchanged in the interim.

17
Stage 1621/02/2025

Delay condonation

The Tribunal granted the respondent additional time to file objections and scheduled the next hearing for March 27, 2025.

18
Stage 1729/01/2025

Delay condonation

The Tribunal allowed the recall application to set aside a cost of Rs. 5,000 imposed on the respondent due to counsel's non-appearance caused by ill health.

19
Stage 1822/01/2025

Delay condonation

No text available.

20
Stage 1915/01/2025

Delay condonation

No text available.

21
Stage 2011/12/2024

Delay condonation

The Tribunal granted a final opportunity for adjournment to the respondent, subject to a cost of Rs. 5,000/- payable to the appellant, and rescheduled the matter for 15.01.2025.

22
Stage 2113/11/2024

Delay condonation

The tribunal adjourned the proceedings following a request from the respondent's counsel and scheduled the matter for consideration of the condonation of delay application on 11-12-2024.

23
Stage 2216/10/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and grounds of appeal, scheduling the next hearing for November 13, 2024.

24
Stage 2305/09/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections against the delay condonation application and grounds of appeal, with a subsequent timeline set for the applicant's reply.

25
Stage 2429/07/2024

Delay condonation

The Tribunal granted the respondent a final 10-day extension to file their vakalatnama and objections, with the appellant permitted to reply within one week thereafter.

26
Stage 2501/07/2024

Delay condonation

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and the grounds of appeal, scheduling the matter for orders on 29.07.2024.

27
Stage 2601/05/2024

Delay condonation

No text available.

28
Stage 2708/04/2024

Delay condonation

The Tribunal granted the appellant one week to file an affidavit of service and scheduled a hearing for the defective appeal on May 1, 2024.

29
Stage 2804/03/2024

Delay condonation

The Tribunal issued a notice to the respondent and outlined the procedural timeline for service of documents, filing objections to the condonation of delay application, and subsequent replies, scheduling the next hearing for April 8, 2024.

30
Stage 29Interim Order

Tribunal Order #0901126008912024-11-09-2025

The Tribunal allowed the application for condonation of a 219-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.

31
Stage 30Interim Order

Tribunal Order #0901126008912024-11-12-2024

The Tribunal granted a final opportunity for adjournment to the respondent, subject to a cost of Rs. 5,000/- payable to the appellant, and rescheduled the matter for 15.01.2025.

32
Stage 31Interim Order

Tribunal Order #0901126008912024-29-01-2025

The Tribunal allowed the recall application to set aside a cost of Rs. 5,000 imposed on the respondent due to counsel's non-appearance caused by ill health.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Deepak Dwivedi

Respondent Advocate(s)

  • Suchita Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126008912024-11-09-2025

The Tribunal allowed the application for condonation of a 219-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126008912024-11-12-2024

The Tribunal granted a final opportunity for adjournment to the respondent, subject to a cost of Rs. 5,000/- payable to the appellant, and rescheduled the matter for 15.01.2025.

INTERIM_ORDEROrder ID: 0901126008912024-29-01-2025

The Tribunal allowed the recall application to set aside a cost of Rs. 5,000 imposed on the respondent due to counsel's non-appearance caused by ill health.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →