up_reraStatus: Completed
CASE ID: 0901126008892022

Appellant / Complainant

Nidhi Pandya

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008892022 by Nidhi Pandya against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016. It further directed the transfer of deposited funds under Section 43(5) to the Regulatory Authority for disposal.

3
Stage 222/12/2022

Delay condonation

The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.

4
Stage 320/12/2022

Delay condonation

The Tribunal granted a request by the appellant's counsel to adjourn the matter and scheduled the appeal for further orders on 22.12.2022.

5
Stage 415/12/2022

Delay condonation

Upon a joint request from the counsels for both parties, the Tribunal adjourned the appeal and scheduled it for further orders on 20.12.2022.

6
Stage 508/12/2022

Delay condonation

The Tribunal noted that no time remained for the hearing and ordered the defective appeal to be listed on 15.12.2022 for further orders.

7
Stage 611/11/2022

Delay condonation

The Tribunal directed the respondent to file their Vakalatnama, objections to the delay condonation application, and a reply to the appeal grounds by the next hearing date. The matter is listed for 08.12.2022 to address the delay condonation application.

8
Stage 711/10/2022

Delay condonation

The Tribunal directed the respondent to file their Vakalatnama, objections to the delay condonation application, and a reply to the grounds of appeal by the next hearing date.

9
Stage 807/09/2022

For Order

The Tribunal directed the respondent to file their Vakalatnama and an objection to the delay condonation application, scheduling the matter for 11.10.2022.

10
Stage 908/08/2022

Notice

The Tribunal noted the service of notice on the respondent and scheduled the matter for September 7, 2022, to consider an application for condonation of delay.

11
Stage 1013/06/2022

Defect Removal

The Tribunal directed the appellant to file a delay condonation application and a certified copy of the impugned order within 15 days and issued notice to the respondent for August 8, 2022.

12
Stage 11Final Ruling Order

Tribunal Order #0901126008892022-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016. It further directed the transfer of deposited funds under Section 43(5) to the Regulatory Authority for disposal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016. It further directed the transfer of deposited funds under Section 43(5) to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016. It further directed the transfer of deposited funds under Section 43(5) to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • | Versus LUCKNOW DEVELOPMENT AUTHORITYLUCKNOW DEVELOPMENT AUTHORITY Counsel for Appellant | .............Respondent |

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126008892022-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016. It further directed the transfer of deposited funds under Section 43(5) to the Regulatory Authority for disposal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →