up_reraStatus: Completed
CASE ID: 0901126008772025

Appellant / Complainant

Gaursons Realtech Private Limited

VS

Respondent

Anushrav Gulati

Developer Firm

gaursons realtech private limited

Disputed Amount

8,79,340

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008772025 by Gaursons Realtech Private Limited against Anushrav Gulati before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 117/04/2026

Defect Removal

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Gaursons Realtech Private Limited because the appellant failed to comply with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

3
Stage 223/03/2026

Defect Removal

The Appellant requested time to compute and deposit the delay interest component in compliance with Section 43(5) of the RERA Act 2016, and the Tribunal granted ten days for this purpose.

4
Stage 318/02/2026

Defect Removal

The Tribunal granted the appellant 10 days to file a rejoinder and scheduled the next hearing for March 23, 2026.

5
Stage 429/01/2026

Defect Removal

The Tribunal granted the appellant ten days to file a rejoinder affidavit and scheduled the next hearing for February 18, 2026.

6
Stage 518/12/2025

Defect Removal

The Tribunal granted the appellant ten days to file a rejoinder affidavit following the respondent's submission of objections and scheduled the next hearing for January 29, 2026.

7
Stage 625/11/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections, with a subsequent week allowed for the appellant's rejoinder, and scheduled the matter for hearing on 18.12.2025.

8
Stage 704/11/2025

Defect Removal

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 25.11.2025.

9
Stage 808/10/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a rejoinder within one week thereafter, with the matter listed for hearing on 04.11.2025.

10
Stage 908/09/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections and a subsequent week for a rejoinder, following an adjournment requested by the appellant, and scheduled the next hearing for 08.10.2025.

11
Stage 1018/08/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections and allowed the appellant one week thereafter to file a rejoinder, with the matter listed for orders on 08.09.2025.

12
Stage 1122/07/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections and directed that a rejoinder be filed within one week thereafter, scheduling the next hearing for 18.08.2025.

13
Stage 1230/05/2025

Defect Removal

The Tribunal granted the respondent 10 days to file objections to the appellant's applications for condonation of delay and waiver of deposit, with a subsequent rejoinder period and a scheduled hearing date of 22.07.2025.

14
Stage 13Interim Order

Tribunal Order #0901126008772025-23-03-2026

The Appellant requested time to compute and deposit the delay interest component in compliance with Section 43(5) of the RERA Act 2016, and the Tribunal granted ten days for this purpose.

15
Stage 14Final Ruling Order

Tribunal Order #0901126008772025-17-04-2026

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Gaursons Realtech Private Limited because the appellant failed to comply with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Gaursons Realtech Private Limited because the appellant failed to comply with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Gaursons Realtech Private Limited because the appellant failed to comply with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samrat Vaish

Respondent Advocate(s)

  • Aditya Tiwari
  • Priyanshu Jaukani

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126008772025-23-03-2026

The Appellant requested time to compute and deposit the delay interest component in compliance with Section 43(5) of the RERA Act 2016, and the Tribunal granted ten days for this purpose.

FINAL_ORDEROrder ID: 0901126008772025-17-04-2026

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Gaursons Realtech Private Limited because the appellant failed to comply with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons realtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →