Complaint registered under Case ID 0901126008702022 by Ghaziabad Development Authority against Ashish Raj before up_rera.
Hearing
The Tribunal dismissed the appeal filed by Ghaziabad Development Authority due to lack of interest and directed the transfer of the appellant's deposited funds to UP RERA after the limitation period for restoration expires.
Hearing
The Tribunal granted the appellant further time to comply with previous orders, subject to an additional cost of Rs. 10,000/- to be paid to the respondent.
Hearing
The Tribunal granted an adjournment to the appellant, subject to a cost of Rs. 10,000/- to be paid by the appellant to the respondent by the next hearing date of 27.05.2025.
Hearing
The Tribunal has scheduled the appeal for further orders or hearing on May 1, 2025, following the appellant's undertaking to file a detailed computation of outstanding dues.
Hearing
The Tribunal granted an adjournment requested by the appellant and scheduled the case for orders on 08.04.2025, with a strict directive that no further adjournments will be permitted.
Hearing
The appellant's counsel filed an application for adjournment, and the tribunal rescheduled the hearing for March 17, 2025.
Hearing
The Tribunal granted a request from the appellant's counsel to adjourn the matter and scheduled the appeal for orders/hearing on 19.02.2025.
Hearing
The Tribunal granted a request for adjournment and rescheduled the hearing for the appeal to 30.01.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted a request for adjournment made by the counsel for the appellant and rescheduled the hearing for January 9, 2025.
Hearing
The Tribunal has granted a request by the appellant's counsel to reschedule the appeal for orders/hearing to 27.11.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to a family casualty and rescheduled the case for orders/hearing on 22.10.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for September 12, 2024.
Hearing
The Tribunal noted that the appellant declined to file a reply to the respondent's objection and scheduled the appeal for a hearing on 15.05.2024.
Hearing
The Tribunal has scheduled the appeal for a hearing on 15.04.2024 due to the absence of both the appellant's and respondent's counsel.
Hearing
The court granted an adjournment requested by the respondent's counsel due to medical urgency and rescheduled the hearing for 11.03.2024.
Hearing
The Tribunal adjourned the proceedings due to a request for adjournment by the respondent's counsel on health grounds and scheduled the next hearing for 01.11.2023.
Hearing
The Tribunal granted a final one-week extension to the appellant to file a reply to the respondent's objections, warning that future adjournments for counsel being 'out of station' will not be permitted and the case may proceed based on available records.
Hearing
The tribunal granted an adjournment as both counsel were unavailable due to being out of station or on medical grounds, rescheduling the matter for hearing on 02.08.2023.
Delay condonation
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's Suo Motu directions, and directed the Registry to convert the defective appeal into a regular appeal.
For Order
The Tribunal granted the applicant one week to file a reply to the grounds of appeal and adjourned the matter to 12.04.2023, pending the examination of the application for condonation of delay.
For Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on 03.04.2023.
For Order
The Tribunal directed the applicant to file a replication/rejoinder to the respondent's reply and scheduled the defective appeal for hearing on 27.01.2023.
Delay condonation
The Tribunal granted the appellant permission to file a replication/rejoinder to the respondent's reply and scheduled the matter for hearing on 19.12.2022.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, with the case scheduled for hearing on 23.11.2022.
Delay condonation
The Tribunal granted a 10-day extension to the respondent to file objections to the application for condonation of delay and the grounds of appeal due to a bereavement in the counsel's family.
Delay condonation
The Tribunal granted the respondent two weeks to file objections to the appeal and the application for condonation of delay, scheduling the next hearing for September 21, 2022.
Delay condonation
The Tribunal adjourned the proceedings due to the counsel for the appellant being on sanctioned leave and directed the filing of the affidavit of service. The matter is listed for 23.08.2022.
Delay condonation
The Tribunal granted the respondent two weeks to file objections to the application for condonation of delay and the grounds of appeal, with the case scheduled for hearing on 04.08.2022.
Defect Removal
The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the account department to verify the credit of a deposited amount of Rs. 3,91,257.00.
Tribunal Order #0901126008702022-27-05-2025
The Tribunal granted the appellant further time to comply with previous orders, subject to an additional cost of Rs. 10,000/- to be paid to the respondent.
Tribunal Order #0901126008702022-01-05-2025
The Tribunal granted an adjournment to the appellant, subject to a cost of Rs. 10,000/- to be paid by the appellant to the respondent by the next hearing date of 27.05.2025.
Tribunal Order #0901126008702022-12-04-2023
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's Suo Motu directions, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126008702022-16-07-2025
The Tribunal dismissed the appeal filed by Ghaziabad Development Authority due to lack of interest and directed the transfer of the appellant's deposited funds to UP RERA after the limitation period for restoration expires.
Tribunal Order #0901126008702022-02-08-2023
The Tribunal granted a final one-week extension to the appellant to file a reply to the respondent's objections, warning that future adjournments for counsel being 'out of station' will not be permitted and the case may proceed based on available records.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by Ghaziabad Development Authority due to lack of interest and directed the transfer of the appellant's deposited funds to UP RERA after the limitation period for restoration expires. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by Ghaziabad Development Authority due to lack of interest and directed the transfer of the appellant's deposited funds to UP RERA after the limitation period for restoration expires.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Arvind Kumar
Respondent Advocate(s)
- Tushar Bahadur
Official RERA Tribunal Orders (5)
The Tribunal granted the appellant further time to comply with previous orders, subject to an additional cost of Rs. 10,000/- to be paid to the respondent.
The Tribunal granted an adjournment to the appellant, subject to a cost of Rs. 10,000/- to be paid by the appellant to the respondent by the next hearing date of 27.05.2025.
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's Suo Motu directions, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal dismissed the appeal filed by Ghaziabad Development Authority due to lack of interest and directed the transfer of the appellant's deposited funds to UP RERA after the limitation period for restoration expires.
The Tribunal granted a final one-week extension to the appellant to file a reply to the respondent's objections, warning that future adjournments for counsel being 'out of station' will not be permitted and the case may proceed based on available records.