up_reraStatus: Completed
CASE ID: 0901126008602023

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Karan Kumar Mahajan

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008602023 by Greater Noida Industrial Development Authority against Karan Kumar Mahajan before up_rera.

Non-Compliance & Execution
2
Stage 104/08/2023

For Order

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of GNIDA's appeal.

3
Stage 224/05/2023

For Order

No text available.

4
Stage 305/05/2023

For Order

The Tribunal granted the Appellant one week to seek instructions regarding the Respondent's application for a refund of deposited funds and scheduled the matter for hearing on 24.05.2023.

5
Stage 419/04/2023

For Order

The court adjourned the proceedings due to the absence of the applicant's counsel and scheduled the application for the release of deposited funds for May 5, 2023.

6
Stage 528/03/2023

For Order

The Tribunal adjourned the application for the release of deposited funds to 19.04.2023 due to the illness of the Appellant's counsel.

7
Stage 627/02/2023

For Order

The Tribunal directed the appellant to file any objections to the respondent's application for release of deposited funds within one week and scheduled the matter for orders on 28.03.2023.

8
Stage 7Final Ruling Order

Tribunal Order #0901126008602023-04-08-2023

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of GNIDA's appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of GNIDA's appeal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of GNIDA's appeal.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126008602023-04-08-2023

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of GNIDA's appeal.