Appellant / Complainant
Deepak Jain, Julie Jain
Respondent
Proview Rishabh Infra Pvt. Ltd., U.P. Real Estate Regulatory Authority Lucknow
proview rishabh infra pvt. ltd.
₹31,62,559
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126008582023 by Deepak Jain, Julie Jain against Proview Rishabh Infra Pvt. Ltd., U.P. Real Estate Regulatory Authority Lucknow before up_rera.
for delivery of Judgment/Order
The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order that had declared the allottees as defaulters, ruling instead that the promoter was in default due to project delays and failure to obtain OC/CC. The Tribunal quashed the impugned order and directed the respondent promoter to pay Rs. 25,000 as litigation costs to the appellants.
Final Hearing
The Tribunal heard arguments from both parties regarding the appeal and has reserved its judgment for a later date.
Hearing
Due to the respondent's failure to file objections, the Tribunal has proceeded ex-parte against Proview Rishabh Infra Pvt. Ltd. and scheduled the appeal for final hearing on 03.11.2025.
Hearing
The Tribunal granted the respondent a final 10-day extension to file objections to the memo of appeal, warning that the matter will proceed ex parte if they fail to comply.
Hearing
The Tribunal granted the appellant 10 days to file a rejoinder affidavit and scheduled the next hearing for October 6, 2025.
Hearing
The Tribunal has scheduled the case for orders on September 8, 2025, and explicitly noted that no further adjournments will be granted to either party.
Delay condonation
The Tribunal allowed the application for condonation of a 187-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The respondent's counsel requested an adjournment, resulting in the matter being rescheduled for orders/hearing on 04.08.2025.
Hearing
The Tribunal granted a request to list the defective appeal for hearing or orders on July 16, 2025.
Hearing
The Tribunal granted a request to list the appeal for orders or hearing on 23.05.2025.
Hearing
The Tribunal granted a request for adjournment filed by the appellant's counsel and scheduled the case for orders on 22.04.2025.
Hearing
The Tribunal has granted a request from the counsels of both parties to list the appeal for orders or hearing on 24.03.2025.
Hearing
The Tribunal has scheduled the appeal for a hearing on February 24, 2025, noting that no parties were present during the proceedings.
Hearing
Upon the joint request of both parties, the tribunal has rescheduled the hearing for Appeal-126/2023 to 04.02.2025.
Hearing
The Tribunal granted the respondent 10 days to file objections and directed the appellant to reply within one week of receiving them, scheduling the next hearing for December 17, 2024.
Hearing
The Tribunal granted the respondent's counsel 10 days to file objections against the appeal and scheduled the next hearing for November 21, 2024.
Hearing
The Tribunal noted the absence of the appellant's counsel and adjourned the matter to 04.10.2024 for orders.
Hearing
The Tribunal granted a request for adjournment due to the appellant's counsel's illness and rescheduled the hearing for the application for condonation of delay to 02.08.2024.
Hearing
The Tribunal has rescheduled the hearing for the defective appeal, including the application for condonation of delay, to July 8, 2024.
Hearing
The Tribunal noted the respondent's intent to file a vakalatnama within three days and rescheduled the hearing for the defective appeal to 08.05.2024.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.
Hearing
The Tribunal granted the applicant one final week to file a reply to the respondent's objections and scheduled the appeal for hearing on 01.03.2024.
For Order
The Tribunal granted a 10-day extension to the appellant to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 12.09.2023.
Defect Removal
The Tribunal issued notice regarding an application for condonation of delay and outlined the procedural steps for service of notice and filing of objections by the parties.
Delay condonation
The Tribunal granted the appellant one week's extension to file a better affidavit in support of their application for condonation of delay and scheduled the matter for hearing on 28.03.2023.
Tribunal Order #0901126008582023-27-10-2025
Due to the respondent's failure to file objections, the Tribunal has proceeded ex-parte against Proview Rishabh Infra Pvt. Ltd. and scheduled the appeal for final hearing on 03.11.2025.
Tribunal Order #0901126008582023-03-02-2026
The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order that had declared the allottees as defaulters, ruling instead that the promoter was in default due to project delays and failure to obtain OC/CC. The Tribunal quashed the impugned order and directed the respondent promoter to pay Rs. 25,000 as litigation costs to the appellants.
Tribunal Order #0901126008582023-04-08-2025
The Tribunal allowed the application for condonation of a 187-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Disposal & Final Award Ruling
The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order that had declared the allottees as defaulters, ruling instead that the promoter was in default due to project delays and failure to obtain OC/CC. The Tribunal quashed the impugned order and directed the respondent promoter to pay Rs. 25,000 as litigation costs to the appellants. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order that had declared the allottees as defaulters, ruling instead that the promoter was in default due to project delays and failure to obtain OC/CC. The Tribunal quashed the impugned order and directed the respondent promoter to pay Rs. 25,000 as litigation costs to the appellants.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Atul Tripathi
Respondent Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Official RERA Tribunal Orders (3)
Due to the respondent's failure to file objections, the Tribunal has proceeded ex-parte against Proview Rishabh Infra Pvt. Ltd. and scheduled the appeal for final hearing on 03.11.2025.
The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order that had declared the allottees as defaulters, ruling instead that the promoter was in default due to project delays and failure to obtain OC/CC. The Tribunal quashed the impugned order and directed the respondent promoter to pay Rs. 25,000 as litigation costs to the appellants.
The Tribunal allowed the application for condonation of a 187-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Need to research all rulings for proview rishabh infra pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.