up_reraStatus: Completed
CASE ID: 0901126008142023

Appellant / Complainant

Jss Buildcon Private Limited

VS

Respondent

Rupali Sethi

Developer Firm

jss buildcon private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

29 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126008142023 by Jss Buildcon Private Limited against Rupali Sethi before up_rera.

2
Stage 130/07/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.

3
Stage 209/07/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 30.07.2025, noting that no further adjournments will be permitted.

4
Stage 314/05/2025

Delay condonation

The Tribunal granted the appellant ten days to file a rejoinder affidavit and scheduled the next hearing for July 9, 2025.

5
Stage 422/04/2025

Delay condonation

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the matter for hearing on May 14, 2025.

6
Stage 526/03/2025

Delay condonation

The Tribunal granted the appellant one week to file a rejoinder and scheduled the hearing for April 22, 2025, to consider the application for condonation of delay.

7
Stage 603/03/2025

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder affidavit to the respondent's objections and scheduled the next hearing for March 26, 2025.

8
Stage 705/02/2025

Delay condonation

The Tribunal granted a request to list the appeal for orders/hearing on 03.03.2025 and directed the parties to exchange pleadings in the interim.

9
Stage 809/01/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent one-week window for the appellant to reply.

10
Stage 927/11/2024

Delay condonation

The Tribunal adjourned the appeal to 09.01.2025 and granted the respondent 10 days to file objections, with the appellant permitted to reply within one week thereafter.

11
Stage 1022/10/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for a hearing on 27.11.2024.

12
Stage 1112/09/2024

Delay condonation

The Tribunal noted that the respondent has received Rs. 6,83,256/- through RERA and no longer objects to compliance with Section 43(5) of the Act; the respondent is granted 10 days to file objections against the appeal.

13
Stage 1227/08/2024

Delay condonation

The Tribunal granted the appellant 10 days to file documents proving that recovered funds have been deposited with RERA and scheduled the matter for orders on 12.09.2024.

14
Stage 1325/07/2024

Delay condonation

The Tribunal granted the appellant a final opportunity to comply with its previous order dated 21.02.2024 by filing the High Court order and proof of payment for Rs 6,83,256/- within one week.

15
Stage 1427/05/2024

Delay condonation

The Tribunal noted the absence of both parties and rescheduled the appeal for hearing/orders to 25.07.2024.

16
Stage 1526/04/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the defective appeal for orders or hearing on May 27, 2024.

17
Stage 1621/03/2024

Delay condonation

The Tribunal noted the illness of the appellant's counsel and ordered the defective appeal to be listed for orders or hearing on 26.04.2024.

18
Stage 1721/02/2024

Delay condonation

The Tribunal addressed objections regarding incomplete compliance with Section 43(5) of the Act, noting that a sum of Rs 6,83,256/- was adjusted following High Court directions, and granted the appellant two days to file supporting documentation.

19
Stage 1811/01/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the matter for hearing on 21.02.2024.

20
Stage 1906/10/2023

Delay condonation

No text available.

21
Stage 2028/08/2023

Delay condonation

No text available.

22
Stage 2110/07/2023

Delay condonation

No text available.

23
Stage 2228/04/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on July 10, 2023.

24
Stage 2317/03/2023

Defect Removal

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed the parties to follow specific service procedures before the next hearing on 28.04.2023.

25
Stage 24Final Ruling Order

Tribunal Order #0901126008142023-30-07-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.

26
Stage 25Interim Order

Tribunal Order #0901126008142023-12-09-2024

The Tribunal noted that the respondent has received Rs. 6,83,256/- through RERA and no longer objects to compliance with Section 43(5) of the Act; the respondent is granted 10 days to file objections against the appeal.

27
Stage 26Interim Order

Tribunal Order #0901126008142023-25-07-2024

The Tribunal granted the appellant a final opportunity to comply with its previous order dated 21.02.2024 by filing the High Court order and proof of payment for Rs 6,83,256/- within one week.

28
Stage 27Interim Order

Tribunal Order #0901126008142023-21-02-2024

The Tribunal addressed objections regarding incomplete compliance with Section 43(5) of the Act, noting that a sum of Rs 6,83,256/- was adjusted following High Court directions, and granted the appellant two days to file supporting documentation.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Singh

Respondent Advocate(s)

  • Mandeep Singh
  • Rohit Jaiswal
  • Jayant Gupta
  • Anjali Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126008142023-30-07-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed the appeal due to a failure to provide sufficient cause for the 263-day delay.

INTERIM_ORDEROrder ID: 0901126008142023-12-09-2024

The Tribunal noted that the respondent has received Rs. 6,83,256/- through RERA and no longer objects to compliance with Section 43(5) of the Act; the respondent is granted 10 days to file objections against the appeal.

INTERIM_ORDEROrder ID: 0901126008142023-25-07-2024

The Tribunal granted the appellant a final opportunity to comply with its previous order dated 21.02.2024 by filing the High Court order and proof of payment for Rs 6,83,256/- within one week.

INTERIM_ORDEROrder ID: 0901126008142023-21-02-2024

The Tribunal addressed objections regarding incomplete compliance with Section 43(5) of the Act, noting that a sum of Rs 6,83,256/- was adjusted following High Court directions, and granted the appellant two days to file supporting documentation.

TathyaGrid RERA Intelligence AI

Need to research all rulings for jss buildcon private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →