Appellant / Complainant
Ashoka Sharma
Respondent
Tyagi Construction Company & others
tyagi construction company
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126008112020 by Ashoka Sharma against Tyagi Construction Company & others before up_rera.
to file objections and its reply
The U.P. Real Estate Appellate Tribunal dismissed Appeal-531/2020 by reference to a prior order dated 12.04.2022 passed in Appeal No. 526/2020.
to file objections and its reply
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for April 12, 2022.
Further Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on March 22, 2022.
Further Order
The Tribunal granted an adjournment requested by the respondent and directed the applicant and the respondent's partner to appear in person on the next date to attempt an amicable settlement.
Hearing
The Tribunal directed the parties to attempt an out-of-court settlement regarding disputed payments and scheduled the matter for further orders on 28.10.2021.
Hearing
The Tribunal noted an allegation by the appellant's husband that the submitted compromise papers contain forged signatures and unauthorized photographs. The matter is listed for 29.09.2021 for further orders, with a directive for parties to appear in person.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to her being out of station and rescheduled the matter for 08.04.2021.
Further Hearing
The matter was adjourned to 12.03.2021 following conflicting claims regarding a potential settlement between the parties.
Tribunal Order #0901126008112020-12-04-2022
The U.P. Real Estate Appellate Tribunal dismissed Appeal-531/2020 by reference to a prior order dated 12.04.2022 passed in Appeal No. 526/2020.
Tribunal Order #0901126008112020-09-09-2021
The Tribunal noted an allegation by the appellant's husband that the submitted compromise papers contain forged signatures and unauthorized photographs. The matter is listed for 29.09.2021 for further orders, with a directive for parties to appear in person.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed Appeal-531/2020 by reference to a prior order dated 12.04.2022 passed in Appeal No. 526/2020. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed Appeal-531/2020 by reference to a prior order dated 12.04.2022 passed in Appeal No. 526/2020.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Fuhar Gupta
- Prashant Kumar Singh
Respondent Advocate(s)
- Sanjay Kumar Srivastava
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed Appeal-531/2020 by reference to a prior order dated 12.04.2022 passed in Appeal No. 526/2020.
The Tribunal noted an allegation by the appellant's husband that the submitted compromise papers contain forged signatures and unauthorized photographs. The matter is listed for 29.09.2021 for further orders, with a directive for parties to appear in person.