up_reraStatus: Completed
CASE ID: 0901126007732023

Appellant / Complainant

Upendra Singh

VS

Respondent

Paramount Probuild Private Limited

Developer Firm

paramount probuild private limited

Disputed Amount

1,35,548

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126007732023 by Upendra Singh against Paramount Probuild Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & Execution
2
Stage 109/02/2024

Delay condonation

The Tribunal condoned the delay in filing the appeal and directed the appellant to submit a representation to the Secretary of the Regulatory Authority to rectify clerical errors regarding the interest calculation period in the amended recovery certificate.

3
Stage 209/10/2023

Delay condonation

No text available.

4
Stage 329/08/2023

Delay condonation

No text available.

5
Stage 411/07/2023

Delay condonation

No text available.

6
Stage 501/05/2023

Delay condonation

No text available.

7
Stage 623/03/2023

Defect Removal

The Tribunal issued a notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, scheduling the matter for hearing on 01.05.2023.

8
Stage 720/03/2023

Defect Removal

No text available.

9
Stage 8Final Ruling Order

Tribunal Order #0901126007732023-09-02-2024

The Tribunal condoned the delay in filing the appeal and directed the appellant to submit a representation to the Secretary of the Regulatory Authority to rectify clerical errors regarding the interest calculation period in the amended recovery certificate.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal condoned the delay in filing the appeal and directed the appellant to submit a representation to the Secretary of the Regulatory Authority to rectify clerical errors regarding the interest calculation period in the amended recovery certificate. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal condoned the delay in filing the appeal and directed the appellant to submit a representation to the Secretary of the Regulatory Authority to rectify clerical errors regarding the interest calculation period in the amended recovery certificate.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the promised date in the agreement till actual possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vipin Verma

Respondent Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126007732023-09-02-2024

The Tribunal condoned the delay in filing the appeal and directed the appellant to submit a representation to the Secretary of the Regulatory Authority to rectify clerical errors regarding the interest calculation period in the amended recovery certificate.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paramount probuild private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →