Appellant / Complainant
Neelam Singh
Respondent
Palash Infratech Pvt Ltd
palash infratech pvt ltd
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126007642021 by Neelam Singh against Palash Infratech Pvt Ltd before up_rera.
Delay condonation
The Tribunal dismissed the appeal because the respondent's project was not registered with RERA, rendering the complaint and appeal non-maintainable under the Supreme Court's ruling in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Further Order
The Tribunal granted the appellant two days to file a reply to the respondent's objections and scheduled the defective appeal for hearing on 12.05.2022 regarding the application for condonation of delay.
Further Order
The Tribunal adjourned the appeal due to the non-appearance of parties and scheduled the matter for further orders on 28.04.2022.
Hearing
The Tribunal granted the appellant's counsel three days to file a reply to the respondent's objections and scheduled the matter for hearing on January 18, 2022.
Hearing
The Tribunal granted the appellant's counsel permission to file a replication/rejoinder affidavit and scheduled the next hearing for January 5, 2022.
Hearing
The Tribunal directed the Registry to verify the Vakalatnama of the applicant's counsel and granted the applicant one week to file a reply to the respondent's objections.
Hearing
The Tribunal granted the appellant a final 10-day extension to file a reply to the respondent's objections and scheduled the next hearing for November 26, 2021.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and directed both parties to exchange pleadings and file originals with the Registry at least seven days before the next hearing on 09.11.2021.
For Order
The Tribunal granted the appellant one week to remove registry defects and directed the respondent to file objections within a week, with subsequent replies to be exchanged via email.
Admission
The Tribunal granted the appellant a one-week extension to rectify procedural defects in the appeal and scheduled the matter for hearing on 15.02.2021.
Tribunal Order #0901126007642021-12-05-2022
The Tribunal dismissed the appeal because the respondent's project was not registered with RERA, rendering the complaint and appeal non-maintainable under the Supreme Court's ruling in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal because the respondent's project was not registered with RERA, rendering the complaint and appeal non-maintainable under the Supreme Court's ruling in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal because the respondent's project was not registered with RERA, rendering the complaint and appeal non-maintainable under the Supreme Court's ruling in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shailender Singh
- Jayendra Singh
Respondent Advocate(s)
- Vijay Vikram
Official RERA Tribunal Orders (1)
The Tribunal dismissed the appeal because the respondent's project was not registered with RERA, rendering the complaint and appeal non-maintainable under the Supreme Court's ruling in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Need to research all rulings for palash infratech pvt ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.