up_reraStatus: Completed
CASE ID: 0901126007442021

Appellant / Complainant

Pushpanjali Constructions Private Limited

VS

Respondent

Shivam Srivastava

Developer Firm

pushpanjali constructions private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126007442021 by Pushpanjali Constructions Private Limited against Shivam Srivastava before up_rera.

2
Stage 115/07/2022

Exchange of pleadings

The Tribunal disposed of the appeal following a settlement between the parties via a Memorandum of Understanding, directing that the entire amount deposited under Section 43(5) of the Act be released to the respondent.

3
Stage 205/05/2022

Exchange of pleadings

No text available.

4
Stage 329/03/2022

Hearing

The Tribunal granted the respondent a final opportunity to file a reply to the grounds of appeal and directed that a copy be emailed to the appellant. The case is scheduled for hearing on 05.05.2022.

5
Stage 408/03/2022

Further Order

The Tribunal granted the respondent ten days to file objections to the grounds of appeal and directed both parties to exchange replies and upload documents on the e-portal before the next hearing scheduled for 29.03.2022.

6
Stage 504/01/2022

Delay condonation

The Tribunal condoned the 31-day delay in filing the appeal, citing COVID-19 pandemic relaxations, and directed the Registry to convert the defective appeal into a regular appeal.

7
Stage 620/12/2021

Further Order

The Tribunal granted the respondent 10 days to file objections against the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the appellant to reply.

8
Stage 724/11/2021

Further Order

The Tribunal directed the respondent to file objections via email after serving a copy to the applicant and scheduled the matter for further orders on 20.12.2021.

9
Stage 817/11/2021

Delay condonation

The Tribunal granted an adjournment application filed by the appellant's counsel and scheduled the next hearing for 24.11.2021, while providing a final opportunity to comply with Section 43(5) of the Act.

10
Stage 922/10/2021

Delay condonation

The Tribunal directed the appellant to remove registry defects and comply with Section 43(5) of the Act within two weeks, while ordering both parties to exchange copies of the application for condonation of delay and subsequent objections via email.

11
Stage 1021/09/2021

Delay condonation

The Tribunal granted the appellant two weeks to rectify registry defects and ensure compliance with Section 43(5) of the Act, warning that failure to do so may result in dismissal.

12
Stage 1103/05/2021

Compliance of section 43(5)

No text available.

13
Stage 1209/04/2021

Compliance of section 43(5)

No text available.

14
Stage 1319/03/2021

Defect Removal

The Tribunal granted the appellant 10 days to comply with Section 43(5) of the Act of 2016 and scheduled the defective appeal for a follow-up hearing on 09.04.2021.

15
Stage 1425/02/2021

Defect Removal

No text available.

16
Stage 1512/02/2021

For Order

The Tribunal granted the appellant three days to comply with Section 43(5) of the Act and scheduled the defective appeal for a hearing on February 25, 2021.

17
Stage 1602/02/2021

Defect Removal

The Tribunal granted the appellant one week to remove registry-indicated defects and scheduled the defective appeal for a subsequent hearing on 12.02.2021.

18
Stage 17Interim Order

Tribunal Order #0901126007442021-04-01-2022

The Tribunal condoned the 31-day delay in filing the appeal, citing COVID-19 pandemic relaxations, and directed the Registry to convert the defective appeal into a regular appeal.

19
Stage 18Final Ruling Order

Tribunal Order #0901126007442021-15-07-2022

The Tribunal disposed of the appeal following a settlement between the parties via a Memorandum of Understanding, directing that the entire amount deposited under Section 43(5) of the Act be released to the respondent.

20
Stage 19Interim Order

Tribunal Order #0901126007442021-22-10-2021

The Tribunal directed the appellant to remove registry defects and comply with Section 43(5) of the Act within two weeks, while ordering both parties to exchange copies of the application for condonation of delay and subsequent objections via email.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the appeal following a settlement between the parties via a Memorandum of Understanding, directing that the entire amount deposited under Section 43(5) of the Act be released to the respondent. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the appeal following a settlement between the parties via a Memorandum of Understanding, directing that the entire amount deposited under Section 43(5) of the Act be released to the respondent.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Respondent Advocate(s)

  • Abhishek Khare
  • Bhupendra Singh
  • Aahuti Agarwal

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126007442021-04-01-2022

The Tribunal condoned the 31-day delay in filing the appeal, citing COVID-19 pandemic relaxations, and directed the Registry to convert the defective appeal into a regular appeal.

FINAL_ORDEROrder ID: 0901126007442021-15-07-2022

The Tribunal disposed of the appeal following a settlement between the parties via a Memorandum of Understanding, directing that the entire amount deposited under Section 43(5) of the Act be released to the respondent.

INTERIM_ORDEROrder ID: 0901126007442021-22-10-2021

The Tribunal directed the appellant to remove registry defects and comply with Section 43(5) of the Act within two weeks, while ordering both parties to exchange copies of the application for condonation of delay and subsequent objections via email.

TathyaGrid RERA Intelligence AI

Need to research all rulings for pushpanjali constructions private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →