up_reraStatus: Completed
CASE ID: 0901126007342024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Pranay Jain

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126007342024 by Lucknow Development Authority against Pranay Jain before up_rera.

Non-Compliance & Execution
2
Stage 121/03/2024

For Order

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority to be released to the respondent during execution proceedings following the dismissal of the appellant's appeal.

3
Stage 213/03/2024

For Order

The court granted a request by the counsel for Lucknow Development Authority (LDA) to adjourn the matter to March 21, 2024, to seek instructions regarding the recovery of funds in execution proceedings.

4
Stage 312/02/2024

For Order

The Tribunal noted the absence of the Lucknow Development Authority and rescheduled the hearing for I.A. No. 506/2024 to March 13, 2024.

5
Stage 4Final Ruling Order

Tribunal Order #0901126007342024-21-03-2024

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority to be released to the respondent during execution proceedings following the dismissal of the appellant's appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority to be released to the respondent during execution proceedings following the dismissal of the appellant's appeal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority to be released to the respondent during execution proceedings following the dismissal of the appellant's appeal.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Respondent Advocate(s)

  • Alok Kumar Tripathi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126007342024-21-03-2024

The Tribunal directed the transfer of the pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority to be released to the respondent during execution proceedings following the dismissal of the appellant's appeal.