up_reraStatus: Completed
CASE ID: 0901126007222022

Appellant / Complainant

U.P. State Industrial Development Corporation Limited

VS

Respondent

Gyanesh Chandra

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126007222022 by U.P. State Industrial Development Corporation Limited against Gyanesh Chandra before up_rera.

2
Stage 131/08/2022

for delivery of Judgment/Order

The appeal was dismissed by reference to a prior order passed in Appeal No. 84/2022.

3
Stage 215/07/2022

Delay condonation

The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's Suo Motu Writ Petition (Civil) No. 3 of 2020 guidelines and directed the Registry to convert the defective appeal into a regular appeal.

4
Stage 301/07/2022

Delay condonation

The Tribunal granted an adjournment requested by the Appellant's counsel due to illness and scheduled the matter for 15.07.2022 to consider the application for condonation of delay.

5
Stage 426/05/2022

Delay condonation

No text available.

6
Stage 513/05/2022

Delay condonation

The Tribunal granted the appellant one week's extension to file a reply to the respondent's objections and scheduled the matter for hearing on May 26, 2022.

7
Stage 625/04/2022

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on the application for condonation of delay on 13.05.2022.

8
Stage 705/04/2022

Notice

The Tribunal granted extensions of time to both the appellant for removing registry defects and the respondent for filing objections to the condonation of delay application, scheduling the next hearing for 25.04.2022.

9
Stage 811/03/2022

Defect Removal

The Tribunal issued notice to the respondent and provided procedural directions for service of the appeal, while directing the applicant to remove registry defects and upload pleadings to the e-portal.

10
Stage 9Interim Order

Tribunal Order #0901126007222022-15-07-2022

The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's Suo Motu Writ Petition (Civil) No. 3 of 2020 guidelines and directed the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126007222022-15-07-2022

The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's Suo Motu Writ Petition (Civil) No. 3 of 2020 guidelines and directed the Registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →