up_reraStatus: Completed
CASE ID: 0901126007182022

Appellant / Complainant

Sahu Land Developers Pvt Ltd

VS

Respondent

Rera Lucknow

Developer Firm

sahu land developers pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126007182022 by Sahu Land Developers Pvt Ltd against Rera Lucknow before up_rera.

2
Stage 102/04/2024

Hearing

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant and the lack of any request for adjournment.

3
Stage 228/02/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the matter for hearing on the application for condonation of delay on 02.04.2024.

4
Stage 324/01/2024

Hearing

The Tribunal adjourned the proceedings due to the absence of the appellant's counsel and scheduled the matter for hearing on the application for condonation of delay on 28.02.2024.

5
Stage 426/10/2023

Hearing

No text available.

6
Stage 514/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a Bar Council of Uttar Pradesh call for lawyers to abstain from judicial work and scheduled the defective appeal for consideration of condonation of delay on 26.10.2023.

7
Stage 626/07/2023

Delay condonation

No text available.

8
Stage 715/05/2023

Delay condonation

The Tribunal granted an adjournment requested by the counsel for the appellant due to personal difficulties and rescheduled the case for 26.07.2023.

9
Stage 825/04/2023

Delay condonation

The Tribunal granted the appellant 10 days to file a better affidavit for condonation of delay regarding an 18-day delay in filing the defective appeal and scheduled the matter for orders on 15.05.2023.

10
Stage 915/03/2023

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to his absence and rescheduled the hearing for April 25, 2023.

11
Stage 1007/02/2023

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the case for hearing on March 15, 2023.

12
Stage 1104/01/2023

Delay condonation

The Tribunal granted an adjournment due to the appellant's counsel's illness and extended the timeline for filing objections and replies, scheduling the next hearing for 07.02.2023.

13
Stage 1208/12/2022

For Order

The Tribunal granted the respondent a 10-day extension to file objections and scheduled the case for hearing on January 4, 2023, regarding the application for condonation of delay.

14
Stage 1314/11/2022

For Order

No text available.

15
Stage 1410/10/2022

For Order

The Tribunal granted a 10-day extension to the respondent for filing objections regarding the condonation of delay and grounds of appeal due to heavy rain, scheduling the next hearing for 14.11.2022.

16
Stage 1508/09/2022

Defect Removal

The Tribunal issued notice to the respondent regarding an application for condonation of delay after the appellant deposited a Rs. 30,000 penalty in compliance with Section 43(5) of the Act.

17
Stage 16Interim Order

Tribunal Order #0901126007182022-08-09-2022

The Tribunal issued notice to the respondent regarding an application for condonation of delay after the appellant deposited a Rs. 30,000 penalty in compliance with Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Sanjai Srivastava

Respondent Advocate(s)

  • Shobhit Mohan Shukla

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126007182022-08-09-2022

The Tribunal issued notice to the respondent regarding an application for condonation of delay after the appellant deposited a Rs. 30,000 penalty in compliance with Section 43(5) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for sahu land developers pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →