Appellant / Complainant
Yamuna Expressway Industrial Development Authority
Respondent
Arvind Kumar Gupta
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126006852026 by Yamuna Expressway Industrial Development Authority against Arvind Kumar Gupta before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 1038-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' for delay.
Delay condonation
The Tribunal granted a request to list the appeal on 11.05.2026 and directed the parties to exchange pleadings in the interim.
Delay condonation
The Tribunal issued a notice to the respondent regarding the application for condonation of delay and directed the parties to follow specific procedures for service of documents and filing objections before the next hearing on 09.04.2026.
Tribunal Order #0901126006852026-11-05-2026
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 1038-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' for delay.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 1038-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' for delay. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 1038-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' for delay.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ankit Raj Chaudhary
Respondent Advocate(s)
- Suchita Singh
Official RERA Tribunal Orders (1)
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 1038-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' for delay.