up_reraStatus: Completed
CASE ID: 0901126006752026

Appellant / Complainant

Yamuna Expressway Industrial Development Authority

VS

Respondent

Pushpendra Juneja

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126006752026 by Yamuna Expressway Industrial Development Authority against Pushpendra Juneja before up_rera.

2
Stage 111/05/2026

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 944-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' under the precedent set by the Supreme Court in Shivamma.

3
Stage 209/04/2026

Delay condonation

The Tribunal has granted a request to adjourn the appeal to 11.05.2026 and directed the parties to exchange pleadings in the interim.

4
Stage 317/03/2026

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder affidavit and scheduled the next hearing for April 9, 2026.

5
Stage 4Final Ruling Order

Tribunal Order #0901126006752026-11-05-2026

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 944-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' under the precedent set by the Supreme Court in Shivamma.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 944-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' under the precedent set by the Supreme Court in Shivamma. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 944-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' under the precedent set by the Supreme Court in Shivamma.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ankit Raj Chaudhary

Respondent Advocate(s)

  • Avinash Singh Vishen

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126006752026-11-05-2026

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 944-day delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic processes do not constitute 'sufficient cause' under the precedent set by the Supreme Court in Shivamma.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →