up_reraStatus: Completed
CASE ID: 0901126006472020

Appellant / Complainant

Pushplata Sharma

VS

Respondent

Eldeco City Ltd., Eldeco Housing and Industries Ltd.

Developer Firm

eldeco housing and industries ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126006472020 by Pushplata Sharma against Eldeco City Ltd., Eldeco Housing and Industries Ltd. before up_rera.

Delay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 126/11/2021

Hearing

The Tribunal dismissed the appeal as 'not pressed' following the respondent's assurance to comply with the RERA order, specifically regarding the execution of a sale deed and the waiver of maintenance charges for one year.

3
Stage 218/11/2021

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to a conflict in the High Court and rescheduled the hearing for 26.11.2021, with a strict directive that no further adjournments will be permitted.

4
Stage 327/09/2021

Hearing

The Tribunal allowed the application for condonation of delay due to a 3-day delay during the COVID-19 pandemic and converted the defective appeal into a regular appeal.

5
Stage 428/04/2021

Hearing

No text available.

6
Stage 502/04/2021

Hearing

No text available.

7
Stage 609/03/2021

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to his LL.M. examinations and rescheduled the hearing for April 2, 2021.

8
Stage 718/02/2021

Delay condonation

No text available.

9
Stage 801/02/2021

Hearing

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and grounds of appeal, with subsequent directions for electronic service and filing of replies.

10
Stage 9Final Ruling Order

Tribunal Order #0901126006472020-26-11-2021

The Tribunal dismissed the appeal as 'not pressed' following the respondent's assurance to comply with the RERA order, specifically regarding the execution of a sale deed and the waiver of maintenance charges for one year.

11
Stage 10Interim Order

Tribunal Order #0901126006472020-27-09-2021

The Tribunal allowed the application for condonation of delay due to a 3-day delay during the COVID-19 pandemic and converted the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal as 'not pressed' following the respondent's assurance to comply with the RERA order, specifically regarding the execution of a sale deed and the waiver of maintenance charges for one year. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal as 'not pressed' following the respondent's assurance to comply with the RERA order, specifically regarding the execution of a sale deed and the waiver of maintenance charges for one year.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from 15.07.2019 till date of execution of sale-deed

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Trivendra Kumar Sharma

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126006472020-26-11-2021

The Tribunal dismissed the appeal as 'not pressed' following the respondent's assurance to comply with the RERA order, specifically regarding the execution of a sale deed and the waiver of maintenance charges for one year.

INTERIM_ORDEROrder ID: 0901126006472020-27-09-2021

The Tribunal allowed the application for condonation of delay due to a 3-day delay during the COVID-19 pandemic and converted the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for eldeco housing and industries ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →