up_reraStatus: Completed
CASE ID: 0901126006042021

Appellant / Complainant

Babu Lal Meena

VS

Respondent

Samiah International Builders

Developer Firm

samiah international builders

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

54 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126006042021 by Babu Lal Meena against Samiah International Builders before up_rera.

2
Stage 112/11/2025

Hearing

The appeal was dismissed due to non-prosecution as no one appeared on behalf of the appellant to press the case.

3
Stage 229/10/2025

Hearing

The Tribunal granted an adjournment application filed by the appellant and rescheduled the appeal for orders/hearing on 12.11.2025, noting that no further adjournments will be permitted.

4
Stage 322/09/2025

Hearing

No text available.

5
Stage 403/09/2025

Hearing

The Tribunal granted a request to list the appeal for orders or hearing on 22.09.2025.

6
Stage 519/08/2025

Hearing

The appellant's counsel requested an adjournment, and the Tribunal has rescheduled the appeal for orders/hearing on 03.09.2025.

7
Stage 628/07/2025

Re-Hearing

The respondent, Samiah International Builders, has undertaken to endeavor to refund Rs. 1,21,000/- to the appellant by the next hearing date, and an affidavit of compliance is required.

8
Stage 707/07/2025

Re-Hearing

The Tribunal granted a request for adjournment from the appellant's counsel and scheduled the case for orders on 28.07.2025, noting that no further adjournments will be permitted.

9
Stage 809/05/2025

Re-Hearing

At the request of the appellant's counsel, the tribunal has adjourned the matter and scheduled the case for orders on 07.07.2025.

10
Stage 917/04/2025

Re-Hearing

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for May 9, 2025.

11
Stage 1020/03/2025

Re-Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 17.04.2025.

12
Stage 1120/02/2025

Re-Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 20.03.2025.

13
Stage 1210/02/2025

Re-Hearing

The Tribunal granted a request for adjournment filed by the appellant's counsel and rescheduled the hearing for 20.02.2025.

14
Stage 1316/01/2025

For Order

The Tribunal has scheduled the appeal for orders/hearing on 10.02.2025 and directed the Registry to issue notices to the parties regarding the fixed date.

15
Stage 1406/08/2024

Hearing

The Tribunal condoned a one-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal to proceed with the hearing on merits.

16
Stage 1504/07/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to the appellant's counsel being unwell and rescheduled the matter for 06.08.2024.

17
Stage 1607/05/2024

Hearing

The Tribunal noted that pleadings have been exchanged and adjourned the matter to 04.07.2024 for consideration of the application for condonation of delay and hearing.

18
Stage 1709/04/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for hearing on the application for condonation of delay on 07.05.2024.

19
Stage 1807/03/2024

Hearing

The Tribunal noted that the appellant's counsel was unavailable and ordered the defective appeal to be listed on 09.04.2024 for consideration of the delay condonation application and hearing.

20
Stage 1902/02/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and scheduled the appeal for hearing on 07.03.2024.

21
Stage 2003/11/2023

Hearing

No text available.

22
Stage 2121/09/2023

Hearing

This text represents the header/caption of an appeal (APPEAL-62/2021) before the U.P. Real Estate Appellate Tribunal, identifying the parties and the presiding members, but contains no substantive ruling or directive.

23
Stage 2204/08/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the defective appeal for hearing on 21.09.2023, specifically to consider the application for condonation of delay.

24
Stage 2324/05/2023

Hearing

No text available.

25
Stage 2415/05/2023

Hearing

No text available.

26
Stage 2503/04/2023

Delay condonation

The Tribunal has scheduled the case for hearing on 15.05.2023 to consider an application for condonation of delay.

27
Stage 2627/02/2023

Delay condonation

The Tribunal granted a request for time by the respondent's counsel to prepare the brief and adjourned the hearing to 03.04.2023.

28
Stage 2725/01/2023

Delay condonation

No text available.

29
Stage 2820/12/2022

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to a scheduling conflict and rescheduled the hearing for the consideration of the delay condonation application to 25.01.2023.

30
Stage 2923/11/2022

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to personal illness and scheduled the matter for consideration of the condonation of delay application on 20.12.2022.

31
Stage 3018/10/2022

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the case for hearing and consideration of the application for condonation of delay on 23.11.2022.

32
Stage 3120/09/2022

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's affidavit and scheduled the matter for hearing on 18.10.2022 regarding the application for condonation of delay.

33
Stage 3231/08/2022

Delay condonation

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the appeal for a hearing on September 20, 2022.

34
Stage 3308/08/2022

Hearing

The Tribunal granted the appellant three days to review documents submitted by the respondent regarding finishing work costs and scheduled the matter for August 31, 2022, to consider the application for condonation of delay.

35
Stage 3427/07/2022

Hearing

The Tribunal directed the respondent to explain the basis for a Rs. 1.2 lac deduction from the appellant's payment within one week and ordered immediate repayment if no justifiable reason is provided.

36
Stage 3519/05/2022

Hearing

The Tribunal directed the respondent to clarify the reasons for a deduction of Rs. 1.2 lacs from the undisputed amount within 20 days and to provide this clarification via email to the appellant.

37
Stage 3618/04/2022

Hearing

The Tribunal directed the appellant's counsel to file a list of dates and events and cases relied upon, and scheduled the matter for hearing on 19.05.2021.

38
Stage 3724/02/2022

Hearing

The Tribunal adjourned the appeal due to the absence of the Appellant and scheduled the matter for hearing on 18.04.2022.

39
Stage 3813/01/2022

Hearing

No text available.

40
Stage 3906/01/2022

Hearing

The Tribunal granted a request from the respondent's counsel to reschedule the matter to January 13, 2022, to report compliance with a previous order.

41
Stage 4017/12/2021

Hearing

The respondent agreed to transfer the undisputed amount to the appellant via RTGS within a week and must provide a written explanation for the deduction of Rs. 1.2 lacs before the next hearing.

42
Stage 4123/11/2021

Delay condonation

The Tribunal adjourned the matter to 17.12.2021, directing the appellant to appear with counsel and the respondent to appear through an authorized decision-maker to explore a potential settlement.

43
Stage 4202/11/2021

Hearing

The Tribunal directed the respondent to file objections to the application for condonation of delay and the grounds of appeal within 10 days, while also mandating the submission of documents via the e-portal and the Registry.

44
Stage 4317/09/2021

Hearing

The Tribunal directed both the applicant and the respondent to appear in person at the next hearing to facilitate a potential settlement.

45
Stage 4419/04/2021

Notice

No text available.

46
Stage 4518/03/2021

For Order

The Tribunal noted that the respondent had not been duly served and ordered the issuance of fresh notices via registered post, email, and dasti, with the matter listed for 19.04.2021.

47
Stage 4627/01/2021

Defect Removal

The Tribunal directed the appellant to rectify registry defects within one week and ordered notice to be issued to the respondent via registered post and email within 10 days.

48
Stage 47Interim Order

Tribunal Order #0901126006042021-28-07-2025

The respondent, Samiah International Builders, has undertaken to endeavor to refund Rs. 1,21,000/- to the appellant by the next hearing date, and an affidavit of compliance is required.

49
Stage 48Interim Order

Tribunal Order #0901126006042021-06-08-2024

The Tribunal condoned a one-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal to proceed with the hearing on merits.

50
Stage 49Interim Order

Tribunal Order #0901126006042021-27-07-2022

The Tribunal directed the respondent to explain the basis for a Rs. 1.2 lac deduction from the appellant's payment within one week and ordered immediate repayment if no justifiable reason is provided.

51
Stage 50Interim Order

Tribunal Order #0901126006042021-19-05-2022

The Tribunal directed the respondent to clarify the reasons for a deduction of Rs. 1.2 lacs from the undisputed amount within 20 days and to provide this clarification via email to the appellant.

52
Stage 51Interim Order

Tribunal Order #0901126006042021-17-12-2021

The respondent agreed to transfer the undisputed amount to the appellant via RTGS within a week and must provide a written explanation for the deduction of Rs. 1.2 lacs before the next hearing.

53
Stage 52Interim Order

Tribunal Order #0901126006042021-02-11-2021

The Tribunal directed the respondent to file objections to the application for condonation of delay and the grounds of appeal within 10 days, while also mandating the submission of documents via the e-portal and the Registry.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samanvya Dhar Dwivedi

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126006042021-28-07-2025

The respondent, Samiah International Builders, has undertaken to endeavor to refund Rs. 1,21,000/- to the appellant by the next hearing date, and an affidavit of compliance is required.

INTERIM_ORDEROrder ID: 0901126006042021-06-08-2024

The Tribunal condoned a one-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal to proceed with the hearing on merits.

INTERIM_ORDEROrder ID: 0901126006042021-27-07-2022

The Tribunal directed the respondent to explain the basis for a Rs. 1.2 lac deduction from the appellant's payment within one week and ordered immediate repayment if no justifiable reason is provided.

INTERIM_ORDEROrder ID: 0901126006042021-19-05-2022

The Tribunal directed the respondent to clarify the reasons for a deduction of Rs. 1.2 lacs from the undisputed amount within 20 days and to provide this clarification via email to the appellant.

INTERIM_ORDEROrder ID: 0901126006042021-17-12-2021

The respondent agreed to transfer the undisputed amount to the appellant via RTGS within a week and must provide a written explanation for the deduction of Rs. 1.2 lacs before the next hearing.

INTERIM_ORDEROrder ID: 0901126006042021-02-11-2021

The Tribunal directed the respondent to file objections to the application for condonation of delay and the grounds of appeal within 10 days, while also mandating the submission of documents via the e-portal and the Registry.

TathyaGrid RERA Intelligence AI

Need to research all rulings for samiah international builders?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →