up_reraStatus: Completed
CASE ID: 0901126005792022

Appellant / Complainant

Sunil Kumar Misra

VS

Respondent

Kanpur Development Authority, Real Estate Regulatory Authority

Disputed Amount

3,31,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility DisputesNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

41 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126005792022 by Sunil Kumar Misra against Kanpur Development Authority, Real Estate Regulatory Authority before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility DisputesNon-Compliance & Execution
2
Stage 129/07/2025

for delivery of Judgment/Order

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sunil Kumar Mishra, ruling that the Kanpur Development Authority had complied with the previous RERA order by adjusting delay interest against outstanding dues, executing the sale deed, and delivering possession of the unit.

3
Stage 227/02/2025

Hearing

The Tribunal noted the absence of the appellant and, upon submission by the respondent's counsel that arguments are complete, reserved the judgment for delivery.

4
Stage 329/01/2025

Hearing

The Tribunal has scheduled the appeal for a final hearing on 27.02.2025 and clarified that no further adjournments will be granted.

5
Stage 403/01/2025

Hearing

The Tribunal adjourned the matter to 29.01.2025 and issued a warning that the case will proceed ex parte if the appellant fails to appear at the next hearing.

6
Stage 516/12/2024

Hearing

The proceedings for Appeal-121/2022 were adjourned at the request of the appellant's counsel and are scheduled to be listed for hearing on January 3, 2025.

7
Stage 628/11/2024

Hearing

No text available.

8
Stage 723/10/2024

Hearing

The Tribunal adjourned the proceedings at the request of the appellant's counsel and scheduled the hearing for November 28, 2024, noting that no further adjournments will be granted.

9
Stage 825/09/2024

Hearing

The Tribunal adjourned the appeal to 23.10.2024 because the respondent's counsel was unavailable due to proceedings in the High Court.

10
Stage 927/08/2024

Hearing

The Tribunal granted an adjournment at the request of the appellant to allow for the uploading of a sale deed and scheduled the matter for hearing on 25.09.2024.

11
Stage 1030/07/2024

Hearing

The Tribunal directed the Kanpur Development Authority to provide the latest status of the flat in question regarding possession and the rectification of reported defects by the next hearing date.

12
Stage 1102/07/2024

Hearing

The Tribunal adjourned the matter to 30.07.2024 for final hearing, noting that the respondent claims the sale deed has been executed and possession of the flat provided.

13
Stage 1202/05/2024

Hearing

The appeal is adjourned to 02.07.2024 because the appellant failed to connect via video conferencing due to poor connectivity, and the court noted a requirement for the appellant's counsel to appear personally in future hearings.

14
Stage 1303/04/2024

Hearing

The Tribunal granted a final one-week extension to the appellant to file the required online complaint before the Regulatory Authority and scheduled the hearing for 02.05.2024.

15
Stage 1404/03/2024

Hearing

The Tribunal granted a request for adjournment by the appellant's counsel and rescheduled the hearing of Appeal-121/2022 to 03.04.2024.

16
Stage 1525/01/2024

Hearing

The Tribunal adjourned the proceedings due to the appellant's absence and directed the appellant to comply with a previous order by filing the online complaint copy and a reply to the respondent's objections.

17
Stage 1627/10/2023

Hearing

No text available.

18
Stage 1715/09/2023

Hearing

The Tribunal noted the absence of both parties and ordered the appeal to be listed for hearing/orders on 27.10.2023.

19
Stage 1811/08/2023

For Order

No text available.

20
Stage 1907/07/2023

For Order

The Tribunal granted the appellant one week's time to place the online complaint filed before the Regulatory Authority on record and scheduled the matter for orders on 11.08.2023.

21
Stage 2027/04/2023

For Order

The Tribunal granted a 10-day extension to the appellant to file a reply to the respondent's objections and adjourned the matter to July 7, 2023, following an adjournment request on health grounds.

22
Stage 2120/03/2023

For Order

No text available.

23
Stage 2209/02/2023

For Order

No text available.

24
Stage 2305/01/2023

For Order

No text available.

25
Stage 2405/12/2022

For Order

No text available.

26
Stage 2509/11/2022

Further Order

The Tribunal found that the documents submitted by the Kanpur Development Authority did not constitute a valid Occupancy Certificate (OC) or Completion Certificate (CC) in accordance with the Act, and directed the respondent to file legally compliant OC/CC before the next hearing.

27
Stage 2610/10/2022

Hearing

This is a formal heading/caption of an appeal case (APPEAL-121/2022) before the U.P. Real Estate Appellate Tribunal; no substantive ruling or directive is contained in this text.

28
Stage 2712/09/2022

Hearing

The Tribunal directed the appellant to take physical possession of the allotted flat and instructed the Respondent (Kanpur Development Authority) to submit copies of the OC/CC and correct calculation details. Both parties were further ordered to submit specific financial clarifications regarding outstanding amounts before the next hearing.

29
Stage 2818/08/2022

Hearing

The Tribunal noted the respondent's commitment to hand over possession of the flat within 10 days and directed the applicant to file objections against the demand letter before the next hearing.

30
Stage 2920/07/2022

Delay condonation

The Tribunal condoned a 22-day delay in filing the appeal based on Supreme Court precedents and directed the Kanpur Development Authority to issue a fresh demand letter within 7 days, with the subsequent execution of the conveyance deed and delivery of possession contingent upon payment.

31
Stage 3027/05/2022

Delay condonation

No text available.

32
Stage 3105/05/2022

Delay condonation

The Tribunal directed the respondent to correct a filing error regarding their objections on the e-portal and granted the appellant ten days to file a reply.

33
Stage 3228/04/2022

Notice

The Tribunal granted the appellant's counsel one week to file an affidavit of service and upload it to the e-portal, subsequently listing the defective appeal for further orders on 05.05.2022.

34
Stage 3305/03/2022

Delay condonation

The Tribunal issued notice to the respondent and directed the appellant to serve the appeal via speed-post and email, scheduling the matter for 28.04.2022 to address the application for condonation of delay.

35
Stage 34Interim Order

Tribunal Order #0901126005792022-30-07-2024

The Tribunal directed the Kanpur Development Authority to provide the latest status of the flat in question regarding possession and the rectification of reported defects by the next hearing date.

36
Stage 35Interim Order

Tribunal Order #0901126005792022-09-11-2022

The Tribunal found that the documents submitted by the Kanpur Development Authority did not constitute a valid Occupancy Certificate (OC) or Completion Certificate (CC) in accordance with the Act, and directed the respondent to file legally compliant OC/CC before the next hearing.

37
Stage 36Final Ruling Order

Tribunal Order #0901126005792022-29-07-2025

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sunil Kumar Mishra, ruling that the Kanpur Development Authority had complied with the previous RERA order by adjusting delay interest against outstanding dues, executing the sale deed, and delivering possession of the unit.

38
Stage 37Interim Order

Tribunal Order #0901126005792022-12-09-2022

The Tribunal directed the appellant to take physical possession of the allotted flat and instructed the Respondent (Kanpur Development Authority) to submit copies of the OC/CC and correct calculation details. Both parties were further ordered to submit specific financial clarifications regarding outstanding amounts before the next hearing.

39
Stage 38Interim Order

Tribunal Order #0901126005792022-18-08-2022

The Tribunal noted the respondent's commitment to hand over possession of the flat within 10 days and directed the applicant to file objections against the demand letter before the next hearing.

40
Stage 39Interim Order

Tribunal Order #0901126005792022-20-07-2022

The Tribunal condoned a 22-day delay in filing the appeal based on Supreme Court precedents and directed the Kanpur Development Authority to issue a fresh demand letter within 7 days, with the subsequent execution of the conveyance deed and delivery of possession contingent upon payment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sunil Kumar Mishra, ruling that the Kanpur Development Authority had complied with the previous RERA order by adjusting delay interest against outstanding dues, executing the sale deed, and delivering possession of the unit. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sunil Kumar Mishra, ruling that the Kanpur Development Authority had complied with the previous RERA order by adjusting delay interest against outstanding dues, executing the sale deed, and delivering possession of the unit.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 04.01.2019 till handing over the physical possession of the unit in question except for the period from 25.03.2020 to 25.09.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 14(3)Section 12Section 11(4)(d)Section 19(6)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prakhar Dixit

Respondent Advocate(s)

  • Bhupendra Singh
  • Somendra Pal Singh

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126005792022-30-07-2024

The Tribunal directed the Kanpur Development Authority to provide the latest status of the flat in question regarding possession and the rectification of reported defects by the next hearing date.

INTERIM_ORDEROrder ID: 0901126005792022-09-11-2022

The Tribunal found that the documents submitted by the Kanpur Development Authority did not constitute a valid Occupancy Certificate (OC) or Completion Certificate (CC) in accordance with the Act, and directed the respondent to file legally compliant OC/CC before the next hearing.

FINAL_ORDEROrder ID: 0901126005792022-29-07-2025

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by Sunil Kumar Mishra, ruling that the Kanpur Development Authority had complied with the previous RERA order by adjusting delay interest against outstanding dues, executing the sale deed, and delivering possession of the unit.

INTERIM_ORDEROrder ID: 0901126005792022-12-09-2022

The Tribunal directed the appellant to take physical possession of the allotted flat and instructed the Respondent (Kanpur Development Authority) to submit copies of the OC/CC and correct calculation details. Both parties were further ordered to submit specific financial clarifications regarding outstanding amounts before the next hearing.

INTERIM_ORDEROrder ID: 0901126005792022-18-08-2022

The Tribunal noted the respondent's commitment to hand over possession of the flat within 10 days and directed the applicant to file objections against the demand letter before the next hearing.

INTERIM_ORDEROrder ID: 0901126005792022-20-07-2022

The Tribunal condoned a 22-day delay in filing the appeal based on Supreme Court precedents and directed the Kanpur Development Authority to issue a fresh demand letter within 7 days, with the subsequent execution of the conveyance deed and delivery of possession contingent upon payment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →