Appellant / Complainant
Lila Dhar Pandey
Respondent
Lucknow Development Authority
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126005392021 by Lila Dhar Pandey against Lucknow Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal allowed the appellant's appeal, modifying a previous order to grant interest compensation for the period from 25.05.2012 to 16.02.2019, and dismissed the cross-appeals filed by the Lucknow Development Authority.
Further Order
The Tribunal heard arguments from both parties and subsequently reserved the judgment for the appeal.
Further Order
The court noted the absence of the appellant and directed the appellant's counsel to file a replication or rejoinder in response to the respondent's reply.
Further Order
The Tribunal directed the respondent, Lucknow Development Authority, to file its Vakalatnama and reply to the grounds of appeal within 10 days and scheduled the next hearing for January 4, 2022.
Further Order
The Tribunal granted Amit Yadav permission to represent the respondent and directed him to file a Vakalatnama and reply by the next hearing date, which is scheduled for 30.11.2021.
Hearing
The Tribunal adjourned the case due to non-appearance of parties and directed that notices be issued via email for the next hearing scheduled on 29.10.2021.
Hearing on Appeal
The Tribunal issued notice to the respondent via registered post and email and scheduled the next hearing for March 17, 2021.
Tribunal Order #0901126005392021-21-10-2022
The Tribunal allowed the appellant's appeal, modifying a previous order to grant interest compensation for the period from 25.05.2012 to 16.02.2019, and dismissed the cross-appeals filed by the Lucknow Development Authority.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appellant's appeal, modifying a previous order to grant interest compensation for the period from 25.05.2012 to 16.02.2019, and dismissed the cross-appeals filed by the Lucknow Development Authority. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appellant's appeal, modifying a previous order to grant interest compensation for the period from 25.05.2012 to 16.02.2019, and dismissed the cross-appeals filed by the Lucknow Development Authority.
Ruling Awarded To
Appellant
Interest Period
from 25.05.2012 to 16.02.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Atul Tripathi
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (1)
The Tribunal allowed the appellant's appeal, modifying a previous order to grant interest compensation for the period from 25.05.2012 to 16.02.2019, and dismissed the cross-appeals filed by the Lucknow Development Authority.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.