CASE ID: 0901126005322023

Appellant / Complainant

Empire Estate Residency Welfare Society

VS

Respondent

Uttar Pradesh Real Estate Regulatory Authority, G. C. Construction and Developers Pvt. Ltd.

Developer Firm

g. c. construction and developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126005322023 by Empire Estate Residency Welfare Society against Uttar Pradesh Real Estate Regulatory Authority, G. C. Construction and Developers Pvt. Ltd. before up_rera.

2
Stage 126/02/2024

Delay condonation

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Empire Estate Residency Welfare Society for want of prosecution due to the non-appearance of both parties.

3
Stage 216/01/2024

Delay condonation

The Tribunal adjourned the proceedings due to the absence of the applicant and scheduled the defective appeal for consideration regarding the application for condonation of delay on 26.02.2024.

4
Stage 312/10/2023

Delay condonation

No text available.

5
Stage 404/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the hearing for 12.10.2023.

6
Stage 510/08/2023

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the matter for orders on 04.09.2023.

7
Stage 617/07/2023

Delay condonation

The Tribunal adjourned the appeal to 10.08.2023 following a request from the appellant's counsel due to health grounds.

8
Stage 713/07/2023

Delay condonation

The Tribunal granted the applicant's counsel 24 hours to prepare his brief and scheduled the defective appeal for hearing on July 17, 2023.

9
Stage 8Final Ruling Order

Tribunal Order #0901126005322023-26-02-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Empire Estate Residency Welfare Society for want of prosecution due to the non-appearance of both parties.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Empire Estate Residency Welfare Society for want of prosecution due to the non-appearance of both parties. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Empire Estate Residency Welfare Society for want of prosecution due to the non-appearance of both parties.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vinod Kumar Yadav

Respondent Advocate(s)

  • Vinod Kumar Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126005322023-26-02-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Empire Estate Residency Welfare Society for want of prosecution due to the non-appearance of both parties.

TathyaGrid RERA Intelligence AI

Need to research all rulings for g. c. construction and developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →