up_reraStatus: Completed
CASE ID: 0901126005242025

Appellant / Complainant

Siddharth Nandan

VS

Respondent

Lucknow Development Authority

Disputed Amount

52,09,349

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126005242025 by Siddharth Nandan against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 125/03/2026

For Order

The Tribunal allowed the appeal and directed the respondent to pay interest at MCLR+1% to the appellant for the delay period from 15.02.2014 to 08.01.2021, ruling that the presence of a High Tension Electricity Wire did not constitute a force majeure event or a valid reason to waive interest obligations under Section 18(1) of the Act 2016.

3
Stage 225/02/2026

for delivery of Judgment/Order

The Tribunal condoned the delay of 1878 days in filing the appeal due to the prolonged illness and dementia of the previous counsel, directing the registry to convert the defective appeal into a regular appeal.

4
Stage 323/02/2026

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and has reserved its order.

5
Stage 402/02/2026

Delay condonation

The case is adjourned to 23.02.2026 for orders due to a technical glitch with the NIC server.

6
Stage 512/01/2026

Delay condonation

The Tribunal granted the appellant ten days to file a rejoinder and scheduled the defective appeal for consideration of the delay condonation application on 02.02.2026.

7
Stage 603/12/2025

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder and scheduled the next hearing for January 12, 2026.

8
Stage 713/11/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for December 3, 2025.

9
Stage 803/11/2025

Delay condonation

The Tribunal granted a joint request from the counsel for both parties to adjourn the appeal and rescheduled the matter for hearing on 13.11.2025.

10
Stage 909/10/2025

Delay condonation

The Tribunal noted the respondent's attempt to settle the matter and adjourned the appeal to 03.11.2025.

11
Stage 1026/09/2025

Delay condonation

The Tribunal granted the respondent seven days to file objections and allowed the appellant three days to file a reply, scheduling the next hearing for 09.10.2025.

12
Stage 1122/09/2025

Delay condonation

No text available.

13
Stage 1222/08/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed the appellant to reply within a week, scheduling the matter for September 22, 2025, to consider an application for condonation of delay.

14
Stage 1301/08/2025

Delay condonation

The Tribunal granted the respondent 10 days to file a Vakalatnama and objections to the delay condonation application and appeal, with the matter scheduled for hearing on 22.08.2025.

15
Stage 1411/07/2025

Delay condonation

The Tribunal noted the respondent's failure to file objections or appear despite sufficient notice and ordered that the appeal be heard ex parte on the next scheduled date of 01.08.2025.

16
Stage 1520/05/2025

Delay condonation

The Tribunal listed a defective appeal for hearing on the application for condonation of delay on 11.07.2025 and directed parties to exchange pleadings in the interim.

17
Stage 1629/04/2025

Delay condonation

The Tribunal noted sufficient service upon the respondent and granted ten days for filing objections to the grounds of appeal, with a subsequent week allowed for the appellant's rejoinder.

18
Stage 1702/04/2025

Delay condonation

The Tribunal issued notice to the respondent and outlined specific procedural timelines for service of documents, filing objections to the condonation of delay application, and subsequent hearings.

19
Stage 18Final Ruling Order

Tribunal Order #0901126005242025-25-03-2026

The Tribunal allowed the appeal and directed the respondent to pay interest at MCLR+1% to the appellant for the delay period from 15.02.2014 to 08.01.2021, ruling that the presence of a High Tension Electricity Wire did not constitute a force majeure event or a valid reason to waive interest obligations under Section 18(1) of the Act 2016.

20
Stage 19Interim Order

Tribunal Order #0901126005242025-25-02-2026

The Tribunal condoned the delay of 1878 days in filing the appeal due to the prolonged illness and dementia of the previous counsel, directing the registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appeal and directed the respondent to pay interest at MCLR+1% to the appellant for the delay period from 15.02.2014 to 08.01.2021, ruling that the presence of a High Tension Electricity Wire did not constitute a force majeure event or a valid reason to waive interest obligations under Section 18(1) of the Act 2016. Awarded in favor of Appellant. Awarded interest rate: MCLR+1 percent.

Disposal Winner: AppellantInterest Rate: MCLR+1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appeal and directed the respondent to pay interest at MCLR+1% to the appellant for the delay period from 15.02.2014 to 08.01.2021, ruling that the presence of a High Tension Electricity Wire did not constitute a force majeure event or a valid reason to waive interest obligations under Section 18(1) of the Act 2016.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1 percent

Interest Period

w.e.f. 15.02.2014 to 08.01.2021

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126005242025-25-03-2026

The Tribunal allowed the appeal and directed the respondent to pay interest at MCLR+1% to the appellant for the delay period from 15.02.2014 to 08.01.2021, ruling that the presence of a High Tension Electricity Wire did not constitute a force majeure event or a valid reason to waive interest obligations under Section 18(1) of the Act 2016.

INTERIM_ORDEROrder ID: 0901126005242025-25-02-2026

The Tribunal condoned the delay of 1878 days in filing the appeal due to the prolonged illness and dementia of the previous counsel, directing the registry to convert the defective appeal into a regular appeal.