up_reraStatus: Completed
CASE ID: 0901126005192021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Nilima Pandey

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126005192021 by Lucknow Development Authority against Nilima Pandey before up_rera.

2
Stage 117/11/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal, while granting respondents liberty to apply for the release of such amounts.

3
Stage 223/11/2021

Notice

The Tribunal granted a stay on recovery proceedings against the appellant pending further orders, noting that the respondent has taken possession of the flat and required statutory payments have been deposited.

4
Stage 330/09/2021

Hearing

The Tribunal issued notice to the respondent via registered post and email and scheduled a hearing for November 23, 2021, to address the limitation application.

5
Stage 409/09/2021

Hearing

The Tribunal directed the appellant to file a CA Certificate regarding the Section 43(5) deposit within three days and ordered the issuance of notice to the respondent.

6
Stage 504/05/2021

Hearing

No text available.

7
Stage 607/04/2021

Hearing

No text available.

8
Stage 716/03/2021

Defect Removal

The Tribunal granted the Lucknow Development Authority a final opportunity to comply with the mandatory provisions of Section 43(5) of the Act before the next hearing date.

9
Stage 808/03/2021

Defect Removal

The Tribunal granted a final one-week extension to the appellant to comply with the order dated 21.01.2021, warning that failure to do so will result in the dismissal of the appeal for non-compliance.

10
Stage 924/02/2021

Defect Removal

The Tribunal directed the appellant to ensure compliance with a previous order dated 21.01.2021 and scheduled the defective appeal for a hearing on 08.03.2021.

11
Stage 1021/01/2021

Defect Removal

The Tribunal directed the Appellant to deposit the balance amount required under Section 43(5) of the Act along with a CA Certificate within two weeks and to file an application for condonation of delay.

12
Stage 11Interim Order

Tribunal Order #0901126005192021-16-03-2021

The Tribunal granted the Lucknow Development Authority a final opportunity to comply with the mandatory provisions of Section 43(5) of the Act before the next hearing date.

13
Stage 12Final Ruling Order

Tribunal Order #0901126005192021-17-11-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal, while granting respondents liberty to apply for the release of such amounts.

14
Stage 13Interim Order

Tribunal Order #0901126005192021-23-11-2021

The Tribunal granted a stay on recovery proceedings against the appellant pending further orders, noting that the respondent has taken possession of the flat and required statutory payments have been deposited.

15
Stage 14Interim Order

Tribunal Order #0901126005192021-08-03-2021

The Tribunal granted a final one-week extension to the appellant to comply with the order dated 21.01.2021, warning that failure to do so will result in the dismissal of the appeal for non-compliance.

16
Stage 15Interim Order

Tribunal Order #0901126005192021-21-01-2021

The Tribunal directed the Appellant to deposit the balance amount required under Section 43(5) of the Act along with a CA Certificate within two weeks and to file an application for condonation of delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal, while granting respondents liberty to apply for the release of such amounts. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal, while granting respondents liberty to apply for the release of such amounts.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Hridesh Srivastava

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126005192021-16-03-2021

The Tribunal granted the Lucknow Development Authority a final opportunity to comply with the mandatory provisions of Section 43(5) of the Act before the next hearing date.

FINAL_ORDEROrder ID: 0901126005192021-17-11-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal, while granting respondents liberty to apply for the release of such amounts.

INTERIM_ORDEROrder ID: 0901126005192021-23-11-2021

The Tribunal granted a stay on recovery proceedings against the appellant pending further orders, noting that the respondent has taken possession of the flat and required statutory payments have been deposited.

INTERIM_ORDEROrder ID: 0901126005192021-08-03-2021

The Tribunal granted a final one-week extension to the appellant to comply with the order dated 21.01.2021, warning that failure to do so will result in the dismissal of the appeal for non-compliance.

INTERIM_ORDEROrder ID: 0901126005192021-21-01-2021

The Tribunal directed the Appellant to deposit the balance amount required under Section 43(5) of the Act along with a CA Certificate within two weeks and to file an application for condonation of delay.