up_reraStatus: Completed
CASE ID: 0901126004832022

Appellant / Complainant

Uttar Pradesh State Industrial Development Authority

VS

Respondent

Om Prakash Yadav

Developer Firm

uttar pradesh state industrial development authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004832022 by Uttar Pradesh State Industrial Development Authority against Om Prakash Yadav before up_rera.

2
Stage 131/08/2022

for delivery of Judgment/Order

The appeal was dismissed by reference to a previous order passed in Appeal No. 84/2022.

3
Stage 215/07/2022

Delay condonation

The order refers the matter to a previous order passed in Appeal No. 84/2022 for directions.

4
Stage 306/07/2022

Delay condonation

Upon the joint request of the counsel for both parties, the tribunal ordered that the appeal be listed along with similar matters on 15.07.2022.

5
Stage 418/05/2022

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on July 6, 2022.

6
Stage 505/05/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the case for hearing on May 18, 2022.

7
Stage 608/04/2022

Defect Removal

The Tribunal directed the applicant to re-upload ID proof and readable annexures, granted the respondent 10 days to file objections and grounds of appeal, and scheduled the matter for May 5, 2022.

8
Stage 717/02/2022

Defect Removal

The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any remaining outstanding amounts before the next hearing.

9
Stage 8Interim Order

Tribunal Order #0901126004832022-17-02-2022

The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any remaining outstanding amounts before the next hearing.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126004832022-17-02-2022

The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any remaining outstanding amounts before the next hearing.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uttar pradesh state industrial development authority?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →