Appellant / Complainant
Pragati Structures Private Limited
Respondent
Secretary Uttar Pradesh Real Estate Regulatory Authority
pragati structures private limited
₹1,00,000
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126004782025 by Pragati Structures Private Limited against Secretary Uttar Pradesh Real Estate Regulatory Authority before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to an unexplained delay of 1924 days in challenging a penalty order.
Delay condonation
The Tribunal granted a request to list the appeal for orders or hearing on 22.09.2025.
Delay condonation
The Tribunal directed the appellant to upload their rejoinder on the portal and scheduled the matter for hearing on the application for condonation of delay on 08.09.2025.
Delay condonation
The Tribunal granted the appellant time to file a rejoinder affidavit and scheduled the hearing for consideration of the application for condonation of delay on 13.08.2025.
Delay condonation
The Tribunal granted the appellant 10 days to file a rejoinder affidavit and scheduled the matter for orders on July 28, 2025.
Delay condonation
The Tribunal granted the respondent seven days to file objections to the application for condonation of delay and the memo of appeal, with a subsequent one-week window for the appellant to file a rejoinder.
Delay condonation
The Tribunal granted the respondent 10 days to file objections and directed the appellant to reply within a week thereafter, scheduling the next hearing for May 6, 2025.
Delay condonation
The Tribunal issued notice to the respondent and directed the applicant to serve the appeal documents via speed-post and email, scheduling the matter for hearing on 10.04.2025.
Tribunal Order #0901126004782025-27-10-2025
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to an unexplained delay of 1924 days in challenging a penalty order.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to an unexplained delay of 1924 days in challenging a penalty order. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to an unexplained delay of 1924 days in challenging a penalty order.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
Respondent Advocate(s)
- Shobhit Mohan Shukla
Official RERA Tribunal Orders (1)
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to an unexplained delay of 1924 days in challenging a penalty order.