up_reraStatus: Completed
CASE ID: 0901126004692022

Appellant / Complainant

U.P. State Industrial Development Corporation Limited

VS

Respondent

Pankaj Mishra

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004692022 by U.P. State Industrial Development Corporation Limited against Pankaj Mishra before up_rera.

2
Stage 131/08/2022

for delivery of Judgment/Order

The appeal was dismissed by the Tribunal via an order previously passed in Appeal No. 84/2022.

3
Stage 215/07/2022

Delay condonation

This is a procedural order referring the matter to a previous order passed in Appeal No. 84/2022.

4
Stage 306/07/2022

Delay condonation

The Tribunal granted a joint request from the counsel for both parties to list the appeal along with similar matters on 15.07.2022.

5
Stage 405/05/2022

Delay condonation

The Tribunal granted the applicant 10 days to file a reply to the respondent's objections and scheduled the case for hearing on May 18, 2022, regarding the application for condonation of delay.

6
Stage 508/04/2022

Defect Removal

The Tribunal directed the appellant to rectify filing defects regarding ID proof and annexures, and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.

7
Stage 617/02/2022

Defect Removal

The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any outstanding amounts before the next hearing.

8
Stage 7Interim Order

Tribunal Order #0901126004692022-17-02-2022

The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any outstanding amounts before the next hearing.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126004692022-17-02-2022

The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any outstanding amounts before the next hearing.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →