Appellant / Complainant
U.P. State Industrial Development Corporation Limited
Respondent
R N Pandey
u.p. state industrial development corporation limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126004672023 by U.P. State Industrial Development Corporation Limited against R N Pandey before up_rera.
For Order
The Tribunal has ordered that the appeal be listed only after the decision is reached in a connected RERA Appeal (No. 37 of 2022) currently pending before the High Court.
Delay condonation
The Tribunal rejected the delay condonation application and dismissed the defective appeal pursuant to a previously issued order in Appeal No. (D) 167/2023.
Delay condonation
The Tribunal ruled that service of notice to the respondent is sufficient based on postal and email delivery, and granted the respondent 10 days to file objections.
Delay condonation
The Tribunal granted the appellant's counsel one week to file an affidavit of service and scheduled the defective appeal for further orders on May 5, 2023.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the applicant to serve the notice and appeal documents via speed-post and email.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
- Ramesh Chandra Mishra
Respondent Advocate(s)
- Deepak Dwivedi