up_reraStatus: Completed
CASE ID: 0901126004672022

Appellant / Complainant

Rajnish Tuli

VS

Respondent

Greenbay Infrastructure Pvt Ltd, Rajnish Tuli, The Real Estate Regulatory Authority

Developer Firm

greenbay infrastructure pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004672022 by Rajnish Tuli against Greenbay Infrastructure Pvt Ltd, Rajnish Tuli, The Real Estate Regulatory Authority before up_rera.

2
Stage 129/01/2024

Delay condonation

The appellant filed an application to withdraw the appeal, stating they are ready to take possession of the plot as per regulatory directions; consequently, the Tribunal allowed the withdrawal and dismissed the appeal as not pressed.

3
Stage 218/01/2024

Delay condonation

The Tribunal adjourned the proceedings due to the absence of counsel for both parties and scheduled the matter for hearing on 29.01.2024 regarding a defective appeal and an application for condonation of delay.

4
Stage 316/10/2023

Delay condonation

No text available.

5
Stage 406/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 16.10.2023.

6
Stage 518/07/2023

Delay condonation

The Tribunal adjourned the proceedings due to the illness of the respondent's counsel and rescheduled the hearing for September 6, 2023.

7
Stage 603/05/2023

Delay condonation

The court granted an adjournment requested by the respondent's counsel due to his absence from the station and rescheduled the matter for July 18, 2023.

8
Stage 722/03/2023

Delay condonation

No text available.

9
Stage 817/02/2023

Hearing

The Tribunal noted the absence of both parties and ordered that the defective appeal be listed for hearing on 22.03.2023.

10
Stage 916/02/2023

Hearing

The Tribunal noted that a similar matter is scheduled for order on 17.02.2022 and adjourned the current case to 17.02.2023 for orders or hearing.

11
Stage 1015/02/2023

Hearing

The Tribunal has adjourned the matter to 16.02.2023 for further hearing.

12
Stage 1131/01/2023

Hearing

The Tribunal has revised the listing of this matter and ordered it to be heard alongside similar cases involving Regulatory Section 63 on February 15, 2023.

13
Stage 1222/12/2022

Delay condonation

The Tribunal heard arguments from both parties regarding Appeal-174/2021 and subsequently reserved the judgment for further delivery.

14
Stage 1325/11/2022

Delay condonation

The Tribunal adjourned the proceedings due to a request from the respondent's counsel for medical reasons and rescheduled the hearing for consideration of the condonation of delay application on 22.12.2022.

15
Stage 1420/10/2022

Delay condonation

The tribunal adjourned the proceedings due to the illness of the appellant's counsel and directed the appellant to file a reply to the respondent's objections within one week.

16
Stage 1528/09/2022

Delay condonation

The Tribunal listed the appeal for orders/hearing on 20.10.2022 following the appellant's counsel stating they do not wish to file a reply.

17
Stage 1626/08/2022

Hearing

The Tribunal granted the appellant permission to file a replication/rejoinder to the respondent's reply and scheduled the appeal for hearing on 28.09.2022.

18
Stage 1718/07/2022

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to the unavailability of senior counsel and rescheduled the hearing for 26.08.2022.

19
Stage 1809/05/2022

Hearing

The Tribunal directed the respondent to file their Vakalatnama, objections against the condonation of delay application, and grounds of appeal within specified timelines, and scheduled the next hearing for 18.07.2022.

20
Stage 1907/04/2022

Defect Removal

The Tribunal granted the appellant three days to remove registry defects and issued notice to the respondent, scheduling the matter for May 9, 2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as not pressed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as not pressed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kailash Prashad Pandey
  • Vishal Agarwal

Respondent Advocate(s)

  • Sarvesh Tiwari
TathyaGrid RERA Intelligence AI

Need to research all rulings for greenbay infrastructure pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →