Appellant / Complainant
Uttar Pradesh State Industrial Development Authority (Formerly Known As Upsidc)
Respondent
Ankur Gupta
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126004572022 by Uttar Pradesh State Industrial Development Authority (Formerly Known As Upsidc) against Ankur Gupta before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed 35 appeals filed by UPSIDA, upholding the Regulatory Authority's order for the developer to deliver possession and pay delay interest at MCLR+1%. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.
Delay condonation
The Tribunal condoned the delay in filing multiple appeals by citing the Supreme Court's Suo Moto Writ (Civil) Petition No. 3/2021 regarding limitation extensions and directed the Registry to convert the defective appeals into regular appeals.
Delay condonation
The Tribunal granted a request from both parties' counsel to list the appeal along with similar matters on 15.07.2022.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the case for hearing on July 6, 2022.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on May 18, 2022.
Defect Removal
The Tribunal directed the applicant to rectify filing defects regarding ID proof and unreadable annexures, and granted the respondent 10 days to file objections to the condonation of delay application.
Defect Removal
The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any outstanding amounts before the next hearing.
Tribunal Order #0901126004572022-31-08-2022
The Tribunal dismissed 35 appeals filed by UPSIDA, upholding the Regulatory Authority's order for the developer to deliver possession and pay delay interest at MCLR+1%. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.
Tribunal Order #0901126004572022-15-07-2022
The Tribunal condoned the delay in filing multiple appeals by citing the Supreme Court's Suo Moto Writ (Civil) Petition No. 3/2021 regarding limitation extensions and directed the Registry to convert the defective appeals into regular appeals.
Tribunal Order #0901126004572022-17-02-2022
The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any outstanding amounts before the next hearing.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed 35 appeals filed by UPSIDA, upholding the Regulatory Authority's order for the developer to deliver possession and pay delay interest at MCLR+1%. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed 35 appeals filed by UPSIDA, upholding the Regulatory Authority's order for the developer to deliver possession and pay delay interest at MCLR+1%. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR + 1 percent
Interest Period
from December 2016/March 2017 till the date of issuance of OC/CC or the date of handing over of possession, whichever is earlier
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (3)
The Tribunal dismissed 35 appeals filed by UPSIDA, upholding the Regulatory Authority's order for the developer to deliver possession and pay delay interest at MCLR+1%. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.
The Tribunal condoned the delay in filing multiple appeals by citing the Supreme Court's Suo Moto Writ (Civil) Petition No. 3/2021 regarding limitation extensions and directed the Registry to convert the defective appeals into regular appeals.
The Tribunal directed the appellant to rectify registry defects and comply with Section 43(5) of the Act by depositing any outstanding amounts before the next hearing.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.