up_reraStatus: Completed
CASE ID: 0901126004552020

Appellant / Complainant

Priyadarshini Misra

VS

Respondent

Wtc Noida Development Pvt Ltd

Developer Firm

wtc noida development pvt ltd

Disputed Amount

24,15,658

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004552020 by Priyadarshini Misra against Wtc Noida Development Pvt Ltd before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 122/03/2022

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order, ruling that 'assured returns' are a separate contractual arrangement and do not exempt a developer from paying interest for project delays. The respondent is directed to pay interest at the rate of MCLR+1% per annum from the agreed possession date (14.10.2018) until the legal offer of possession with OC/CC.

3
Stage 225/11/2021

Hearing

The Tribunal heard arguments regarding an appeal against a RERA order concerning the denial of interest under Section 18 due to pre-possession commercial arrangements; judgment has been reserved.

4
Stage 302/11/2021

Hearing

The Tribunal noted the exchange of pleadings and scheduled the case for a hearing on 25.11.2021, stipulating that no further adjournments will be granted on that date.

5
Stage 420/09/2021

Hearing

The Tribunal adjourned the appeal due to the absence of the respondent's counsel and directed both parties to file and exchange lists of dates, events, and relied-upon case law.

6
Stage 520/04/2021

Hearing

No text available.

7
Stage 619/03/2021

Delay condonation

The Tribunal allowed the application for condonation of delay, converted the defective appeal into a regular appeal, and directed the respondent to file a reply within 15 days.

8
Stage 722/02/2021

Notice

No text available.

9
Stage 818/01/2021

For Order

No text available.

10
Stage 916/12/2020

Defect Removal

No text available.

11
Stage 10Interim Order

Tribunal Order #0901126004552020-25-11-2021

The Tribunal heard arguments regarding an appeal against a RERA order concerning the denial of interest under Section 18 due to pre-possession commercial arrangements; judgment has been reserved.

12
Stage 11Interim Order

Tribunal Order #0901126004552020-19-03-2021

The Tribunal allowed the application for condonation of delay, converted the defective appeal into a regular appeal, and directed the respondent to file a reply within 15 days.

13
Stage 12Final Ruling Order

Tribunal Order #0901126004552020-22-03-2022

The Tribunal set aside the Regulatory Authority's order, ruling that 'assured returns' are a separate contractual arrangement and do not exempt a developer from paying interest for project delays. The respondent is directed to pay interest at the rate of MCLR+1% per annum from the agreed possession date (14.10.2018) until the legal offer of possession with OC/CC.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order, ruling that 'assured returns' are a separate contractual arrangement and do not exempt a developer from paying interest for project delays. The respondent is directed to pay interest at the rate of MCLR+1% per annum from the agreed possession date (14.10.2018) until the legal offer of possession with OC/CC. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order, ruling that 'assured returns' are a separate contractual arrangement and do not exempt a developer from paying interest for project delays. The respondent is directed to pay interest at the rate of MCLR+1% per annum from the agreed possession date (14.10.2018) until the legal offer of possession with OC/CC.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

from 14.10.2018 till the date of legal offer of possession after obtaining OC/CC

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ansh Agarwal
  • U.K. Mishra
  • S.S. Mishra

Respondent Advocate(s)

  • Shobhit Mohan Shukla
  • Dilip Mani
  • Anup Gupta
  • Neelam Gupta

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126004552020-25-11-2021

The Tribunal heard arguments regarding an appeal against a RERA order concerning the denial of interest under Section 18 due to pre-possession commercial arrangements; judgment has been reserved.

INTERIM_ORDEROrder ID: 0901126004552020-19-03-2021

The Tribunal allowed the application for condonation of delay, converted the defective appeal into a regular appeal, and directed the respondent to file a reply within 15 days.

FINAL_ORDEROrder ID: 0901126004552020-22-03-2022

The Tribunal set aside the Regulatory Authority's order, ruling that 'assured returns' are a separate contractual arrangement and do not exempt a developer from paying interest for project delays. The respondent is directed to pay interest at the rate of MCLR+1% per annum from the agreed possession date (14.10.2018) until the legal offer of possession with OC/CC.

TathyaGrid RERA Intelligence AI

Need to research all rulings for wtc noida development pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →