up_reraStatus: Completed
CASE ID: 0901126004352026

Appellant / Complainant

Annika Promoters Private Limited

VS

Respondent

Pawan Kumar, Bharati Sharma, Uttar Pradesh Real Estate Regulatory Authority

Developer Firm

annika promoters private limited

Disputed Amount

60,70,734

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004352026 by Annika Promoters Private Limited against Pawan Kumar, Bharati Sharma, Uttar Pradesh Real Estate Regulatory Authority before up_rera.

Non-Compliance & Execution
2
Stage 129/04/2026

Defect Removal

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Annika Promoters Private Limited due to non-compliance with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

3
Stage 220/04/2026

Defect Removal

The Tribunal granted the appellant, Annika Promoters Private Limited, a final extension of time to comply with Section 43(5) of the RERA Act, 2016, by depositing the recovery amount, noting that no further opportunities will be provided.

4
Stage 323/03/2026

Defect Removal

The Tribunal granted the respondent 10 days to file objections, with the appellant directed to reply within a week thereafter, and scheduled the next hearing for 20.04.2026.

5
Stage 418/02/2026

Defect Removal

The Tribunal issued a notice to the respondent regarding an application for waiver (IA No. 165 of 2026) and outlined the procedural steps for service of notice and filing of objections.

6
Stage 5Final Ruling Order

Tribunal Order #0901126004352026-29-04-2026

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Annika Promoters Private Limited due to non-compliance with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

7
Stage 6Interim Order

Tribunal Order #0901126004352026-20-04-2026

The Tribunal granted the appellant, Annika Promoters Private Limited, a final extension of time to comply with Section 43(5) of the RERA Act, 2016, by depositing the recovery amount, noting that no further opportunities will be provided.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Annika Promoters Private Limited due to non-compliance with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Annika Promoters Private Limited due to non-compliance with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ansh Kulshrestha

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126004352026-29-04-2026

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Annika Promoters Private Limited due to non-compliance with the mandatory pre-deposit requirement under Section 43(5) of the RERA Act, 2016.

INTERIM_ORDEROrder ID: 0901126004352026-20-04-2026

The Tribunal granted the appellant, Annika Promoters Private Limited, a final extension of time to comply with Section 43(5) of the RERA Act, 2016, by depositing the recovery amount, noting that no further opportunities will be provided.

TathyaGrid RERA Intelligence AI

Need to research all rulings for annika promoters private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →