up_reraStatus: Completed
CASE ID: 0901126004182023

Appellant / Complainant

Antriksh Engneers Pvt Ltd

VS

Respondent

Uday Bhan Upadhaya

Developer Firm

antriksh engneers pvt ltd

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of Investment

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004182023 by Antriksh Engneers Pvt Ltd against Uday Bhan Upadhaya before up_rera.

Refund of Investment
2
Stage 128/02/2025

Delay condonation

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with a directive that the appellant-promoter is entitled to a refund of the amount deposited with RERA within 45 days of filing the certified order.

3
Stage 212/02/2025

Delay condonation

The Tribunal granted the appellant seven days to file a rejoinder affidavit and scheduled the appeal for hearing on 28.02.2025.

4
Stage 323/01/2025

Delay condonation

The Tribunal granted the appellant a one-week extension to file a rejoinder affidavit and scheduled the next hearing for February 12, 2025.

5
Stage 410/01/2025

Delay condonation

The Tribunal granted time to file a rejoinder affidavit and scheduled the appeal for orders/hearing on 23.01.2025.

6
Stage 520/11/2024

For Order

The Tribunal rejected the respondent's application to recall its previous order, finding no misrepresentation occurred, and scheduled the appeal for hearing on 10.01.2025.

7
Stage 615/10/2024

For Order

The Tribunal granted the respondent's application to recall the dismissal of their previous application (RA No. D663/2023) due to counsel's absence, restoring it to its original number and scheduling a hearing for 20.11.2024.

8
Stage 704/09/2024

For Order

The Tribunal granted an adjournment due to the counsel's personal bereavement and rescheduled the hearing for the defective appeal to 15.10.2024.

9
Stage 805/08/2024

For Order

The Tribunal granted the appellant seven days to file objections against the respondent's recall application and scheduled the matter for consideration on 04.09.2024.

10
Stage 910/07/2024

For Order

The Tribunal granted an adjournment requested by the respondent and directed the appellant to file objections to a recall application within seven days, scheduling the next hearing for August 5, 2024.

11
Stage 1010/05/2024

For Order

The Tribunal adjourned the matter to 10.07.2024 to allow the parties an opportunity to pursue an amicable settlement.

12
Stage 1109/04/2024

For Order

The Tribunal granted a request from the appellant's counsel to reschedule the appeal for hearing or orders to 10.05.2024.

13
Stage 1205/03/2024

For Order

The Tribunal dismissed the respondent's application (RA No. D663 of 2023) for want of prosecution due to non-appearance, and scheduled a hearing for the defective appeal on 09.04.2024.

14
Stage 1325/01/2024

For Order

The Tribunal granted the applicant a one-week extension to file a reply to the respondent's objection regarding the recall application of the order dated 13.02.2023.

15
Stage 1427/10/2023

For Order

No text available.

16
Stage 1515/09/2023

For Order

The Tribunal granted the appellant's counsel one week to file objections regarding the application for recall of the order dated 13.02.2023 and scheduled the matter for hearing on 27.10.2023.

17
Stage 1627/07/2023

For Order

No text available.

18
Stage 1706/07/2023

For Order

The Tribunal granted the appellant's counsel a one-week extension to file a response to the application for recall of the order dated 13.02.2023 and scheduled the defective appeal for hearing on 27.07.2023.

19
Stage 1829/05/2023

For Order

The Tribunal granted the appellant a one-week extension to file objections to an application for recall of the order dated 13.02.2023 and adjourned the matter to 06.07.2023.

20
Stage 1902/05/2023

For Order

The Tribunal granted the appellant one week to file objections to the respondent's application for recall of the order dated 13.02.2023 and scheduled the matter for hearing on 29.05.2023.

21
Stage 2021/03/2023

For Order

No text available.

22
Stage 2113/02/2023

Defect Removal

The Tribunal granted the applicant's application for waiver of the mandatory deposit required under Section 43(5) of the Act, ruling that the previously deposited amount of Rs. 1,07,00,000/- held by the Tehsildar, Dadri, satisfies the requirement for entertaining the appeal.

23
Stage 22Final Ruling Order

Tribunal Order #0901126004182023-28-02-2025

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with a directive that the appellant-promoter is entitled to a refund of the amount deposited with RERA within 45 days of filing the certified order.

24
Stage 23Interim Order

Tribunal Order #0901126004182023-05-03-2024

The Tribunal dismissed the respondent's application (RA No. D663 of 2023) for want of prosecution due to non-appearance, and scheduled a hearing for the defective appeal on 09.04.2024.

25
Stage 24Interim Order

Tribunal Order #0901126004182023-13-02-2023

The Tribunal granted the applicant's application for waiver of the mandatory deposit required under Section 43(5) of the Act, ruling that the previously deposited amount of Rs. 1,07,00,000/- held by the Tehsildar, Dadri, satisfies the requirement for entertaining the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with a directive that the appellant-promoter is entitled to a refund of the amount deposited with RERA within 45 days of filing the certified order. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with a directive that the appellant-promoter is entitled to a refund of the amount deposited with RERA within 45 days of filing the certified order.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare
  • Aahuti Agarwal

Respondent Advocate(s)

  • Shivendra Rao

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126004182023-28-02-2025

The appeal was dismissed as withdrawn following an out-of-court settlement between the parties, with a directive that the appellant-promoter is entitled to a refund of the amount deposited with RERA within 45 days of filing the certified order.

INTERIM_ORDEROrder ID: 0901126004182023-05-03-2024

The Tribunal dismissed the respondent's application (RA No. D663 of 2023) for want of prosecution due to non-appearance, and scheduled a hearing for the defective appeal on 09.04.2024.

INTERIM_ORDEROrder ID: 0901126004182023-13-02-2023

The Tribunal granted the applicant's application for waiver of the mandatory deposit required under Section 43(5) of the Act, ruling that the previously deposited amount of Rs. 1,07,00,000/- held by the Tehsildar, Dadri, satisfies the requirement for entertaining the appeal.