up_reraStatus: Completed
CASE ID: 0901126004122019

Appellant / Complainant

Amit Srivastava

VS

Respondent

Ifci Infrastucture Development Limited(Iidl)

Developer Firm

ifci infrastucture development limited(iidl)

Disputed Amount

40,52,200

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004122019 by Amit Srivastava against Ifci Infrastucture Development Limited(Iidl) before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional Misrepresentation
2
Stage 129/05/2023

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal set aside the RERA Authority's order and directed the respondent to pay interest at the rate of MCLR + 1% per annum for the 52-month delay in handing over possession, calculated from the proposed possession date until the actual offer of possession.

3
Stage 204/01/2023

Hearing

The Tribunal heard arguments from both the appellant and respondent, but the judgment has been reserved for a later date.

4
Stage 302/12/2022

Final Hearing

The Tribunal allowed the appellant to argue the case in person and directed the Registry to summon the RERA records for Complaint No. 1220172407 to examine the issue of compensation for delayed possession.

5
Stage 423/11/2022

Final Hearing

The Tribunal permitted the appellant, Amit Srivastava, to file an application to argue the case in person and disengage his counsel due to his lawyer's unavailability.

6
Stage 519/11/2022

Final Hearing

The Tribunal granted an adjournment of the proceedings due to the illness of the appellant's counsel and rescheduled the hearing for 23.11.2022.

7
Stage 614/10/2022

Final Hearing

No text available.

8
Stage 715/09/2022

Final Hearing

No text available.

9
Stage 831/08/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his absence from the station and rescheduled the hearing for 15.09.2022.

10
Stage 910/08/2022

Final Hearing

The Tribunal granted a joint request from the counsels of both parties to reschedule the hearing of Appeal-270/2019 to 31.08.2022.

11
Stage 1001/07/2022

Final Hearing

No text available.

12
Stage 1126/04/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for July 1, 2022.

13
Stage 1216/03/2022

Final Hearing

The Tribunal adjourned the case due to the absence of both parties and scheduled it for a final hearing on 26.04.2022.

14
Stage 1328/02/2022

Final Hearing

No text available.

15
Stage 1405/01/2022

Hearing

The Tribunal allowed the applicant's application to recall the dismissal order dated 23.10.2020, restoring the appeal to its original number and scheduling a hearing for 18.01.2022.

16
Stage 1510/12/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on January 5, 2022.

17
Stage 1610/11/2021

Hearing

No text available.

18
Stage 1707/10/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a personal emergency and rescheduled the matter for 10.11.2021.

19
Stage 1822/04/2021

Delay condonation

No text available.

20
Stage 1926/03/2021

Hearing on Recall App

No text available.

21
Stage 2005/03/2021

Delay condonation

The Tribunal noted that lawyers were abstaining from work due to a bar association call and listed the application for condonation of delay in filing a recall application for hearing on 26.03.2021.

22
Stage 2117/02/2021

Hearing on Appeal

The Tribunal granted a request for adjournment from the respondent's counsel and rescheduled the appeal for hearing on 05.03.2021.

23
Stage 2221/01/2021

Hearing on Appeal

No text available.

24
Stage 23Final Ruling Order

Tribunal Order #0901126004122019-29-05-2023

The U.P. Real Estate Appellate Tribunal set aside the RERA Authority's order and directed the respondent to pay interest at the rate of MCLR + 1% per annum for the 52-month delay in handing over possession, calculated from the proposed possession date until the actual offer of possession.

25
Stage 24Interim Order

Tribunal Order #0901126004122019-02-12-2022

The Tribunal allowed the appellant to argue the case in person and directed the Registry to summon the RERA records for Complaint No. 1220172407 to examine the issue of compensation for delayed possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal set aside the RERA Authority's order and directed the respondent to pay interest at the rate of MCLR + 1% per annum for the 52-month delay in handing over possession, calculated from the proposed possession date until the actual offer of possession. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal set aside the RERA Authority's order and directed the respondent to pay interest at the rate of MCLR + 1% per annum for the 52-month delay in handing over possession, calculated from the proposed possession date until the actual offer of possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the proposed date of possession till offer of possession on 26.09.2017

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Waseeq Uddin Ahmed

Respondent Advocate(s)

  • Anurag Arora

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126004122019-29-05-2023

The U.P. Real Estate Appellate Tribunal set aside the RERA Authority's order and directed the respondent to pay interest at the rate of MCLR + 1% per annum for the 52-month delay in handing over possession, calculated from the proposed possession date until the actual offer of possession.

INTERIM_ORDEROrder ID: 0901126004122019-02-12-2022

The Tribunal allowed the appellant to argue the case in person and directed the Registry to summon the RERA records for Complaint No. 1220172407 to examine the issue of compensation for delayed possession.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ifci infrastucture development limited(iidl)?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →