Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126004042024 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Smita Singh Deo before up_rera.
Delay condonation
The appeal was dismissed for non-prosecution as no one appeared on behalf of the appellant to press the defective appeal.
Delay condonation
The Tribunal adjourned the matter to 04.12.2024 for orders due to advocates abstaining from judicial work following a Bar Council resolution.
Delay condonation
The Tribunal adjourned the matter to 04.11.2024, granting the appellant a final opportunity to upload settlement documents and noting that no further adjournments will be permitted.
Delay condonation
The Tribunal granted the appellant three days to upload a settlement agreement between the parties and directed the respondent to file any objections within a week thereafter.
Delay condonation
The Tribunal granted the appellant a final seven-day extension to file a rejoinder and directed them to provide a soft copy to the respondent, scheduling the next hearing for 22.08.2024.
Delay condonation
The Tribunal has listed the defective appeal for orders on 24.07.2024.
Delay condonation
The Tribunal granted the appellant one week's time to file a rejoinder affidavit and scheduled the next hearing for July 10, 2024.
Delay condonation
The Tribunal noted the illness of the respondent's counsel and ordered the defective appeal to be listed for orders on 09.05.2024.
Delay condonation
The Tribunal refers the parties to a previous order passed in Appeal No. D 27/2024 regarding the current matter.
Delay condonation
The Tribunal verified the appellant's compliance with Section 43(5) of the Act via a deposit of Rs 11,06,283/- and issued notice to the respondent regarding the application for condonation of delay and grounds of appeal.
Tribunal Order #0901126004042024-13-02-2024
The Tribunal verified the appellant's compliance with Section 43(5) of the Act via a deposit of Rs 11,06,283/- and issued notice to the respondent regarding the application for condonation of delay and grounds of appeal.
Tribunal Disposal & Final Award Ruling
Dismissed for non-prosecution Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed for non-prosecution
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Naveen Kumar Tiwari
Respondent Advocate(s)
- Ashutosh Yadav
Official RERA Tribunal Orders (1)
The Tribunal verified the appellant's compliance with Section 43(5) of the Act via a deposit of Rs 11,06,283/- and issued notice to the respondent regarding the application for condonation of delay and grounds of appeal.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.