up_reraStatus: Completed
CASE ID: 0901126004032019

Appellant / Complainant

Great Value Projects India Pvt. Ltd.

VS

Respondent

Ashish Malla

Developer Firm

great value projects india pvt. ltd.

Disputed Amount

66,00,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

7 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126004032019 by Great Value Projects India Pvt. Ltd. against Ashish Malla before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 113/01/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal confirmed the refund of the deposited amount to the respondent due to project delay but modified the interest rate from 18% per annum to MCLR+1% per annum and directed the respondent to seek compensation through an Adjudicating Officer.

3
Stage 225/03/2021

Rest Arg. on Merit

No text available.

4
Stage 329/01/2021

Hearing

The Tribunal granted the respondent one week to submit supporting rulings via email and post, and adjourned the matter to 25.03.2021 for further arguments.

5
Stage 414/12/2020

Hearing

No text available.

6
Stage 5Final Ruling Order

Tribunal Order #0901126004032019-13-01-2022

The U.P. Real Estate Appellate Tribunal confirmed the refund of the deposited amount to the respondent due to project delay but modified the interest rate from 18% per annum to MCLR+1% per annum and directed the respondent to seek compensation through an Adjudicating Officer.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal confirmed the refund of the deposited amount to the respondent due to project delay but modified the interest rate from 18% per annum to MCLR+1% per annum and directed the respondent to seek compensation through an Adjudicating Officer. Awarded in favor of Partial. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: PartialInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal confirmed the refund of the deposited amount to the respondent due to project delay but modified the interest rate from 18% per annum to MCLR+1% per annum and directed the respondent to seek compensation through an Adjudicating Officer.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the date of deposit till the date of actual payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Misra

Respondent Advocate(s)

  • In Person

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126004032019-13-01-2022

The U.P. Real Estate Appellate Tribunal confirmed the refund of the deposited amount to the respondent due to project delay but modified the interest rate from 18% per annum to MCLR+1% per annum and directed the respondent to seek compensation through an Adjudicating Officer.

TathyaGrid RERA Intelligence AI

Need to research all rulings for great value projects india pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →