up_reraStatus: Completed
CASE ID: 0901126003992023

Appellant / Complainant

Anju Kumari

VS

Respondent

Ajpa Parishad Sehkari Awas Samiti Ltd

Developer Firm

ajpa parishad sehkari awas samiti ltd

Disputed Amount

62,14,960

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003992023 by Anju Kumari against Ajpa Parishad Sehkari Awas Samiti Ltd before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationNon-Compliance & Execution
2
Stage 124/01/2025

Hearing

The Tribunal ruled that a promoter cannot use an out-of-court settlement to curtail an allottee's statutory right to receive delay interest under Section 18(1) of the RERA Act, 2016. Consequently, it set aside the Regulatory Authority's dismissal of the execution petition and ordered the restoration of proceedings to enforce the payment of interest.

3
Stage 221/01/2025

Hearing

The Tribunal scheduled the appeal for hearing on 24.01.2025 and ordered that the matter will proceed ex parte against the respondent due to their absence.

4
Stage 312/12/2024

Hearing

The Tribunal noted that the respondent refused to accept the notice, deemed service sufficient, and scheduled the appeal for hearing on 21.01.2025.

5
Stage 418/11/2024

Hearing

The Tribunal directed that the appeal be listed for orders or hearing on 12.12.2024, referencing a previous order passed in a related matter.

6
Stage 503/10/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to his absence from the station and rescheduled the matter for orders on 18.11.2024.

7
Stage 602/09/2024

Hearing

The Tribunal has listed Appeal-80/2023 for a hearing on 03.10.2024, referencing a previous order passed in a related appeal.

8
Stage 721/08/2024

Hearing

The Tribunal granted the appellant a seven-day extension to comply with the previous order dated 08.08.2024 and scheduled the next hearing for 02.09.2024.

9
Stage 808/08/2024

Hearing

The Tribunal noted the respondent's failure to comply with previous orders and warned that the President and Secretary may face proceedings under Section 64 of the Act for non-compliance. The appellant was granted one week to provide details regarding the current office bearers of the respondent organization.

10
Stage 922/07/2024

Hearing

The Tribunal refers the parties to a previous order passed in Appeal No. 668/2022 for directions regarding this matter.

11
Stage 1022/05/2024

Hearing

The Tribunal granted the respondent a 10-day extension to submit a calculation chart and comply with previous orders due to a change in the management committee's composition.

12
Stage 1107/05/2024

Hearing

The Tribunal rejected the respondent's application for an extension of time due to procedural defects and ordered the President and Secretary of the respondent to appear on the next date to show cause why proceedings should not be initiated against them under Section 64 of the Act for non-compliance.

13
Stage 1215/04/2024

Hearing

The Tribunal granted the respondent one week to calculate and submit a statement detailing the total amount payable to the appellant under the order dated 10.04.2019, after accounting for payments already made during settlement.

14
Stage 1321/03/2024

Hearing

The Tribunal directs the parties to refer to the order previously passed in Appeal No. 669/2022 for the relevant orders.

15
Stage 1406/03/2024

Hearing

The court has scheduled the hearing for Appeal-80/2023 to take place on March 21, 2024, following a joint request from the counsel of both parties.

16
Stage 1516/02/2024

Hearing

The Tribunal directs the parties to refer to the order passed in Appeal No. 669/2022 for the relevant directives and orders.

17
Stage 1609/01/2024

Hearing

The Tribunal noted the appellant's counsel is on leave and scheduled the appeal for a hearing/orders on 16.02.2024.

18
Stage 1703/10/2023

Hearing

No text available.

19
Stage 1812/09/2023

Hearing

No text available.

20
Stage 1921/07/2023

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the appeal for hearing on 12.09.2023.

21
Stage 2010/05/2023

Hearing

No text available.

22
Stage 2129/03/2023

For Order

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and established a timeline for subsequent replies and e-portal uploads before listing the matter for hearing on 10.05.2023.

23
Stage 2220/02/2023

Admission

The Tribunal issued a notice to the respondent and outlined specific procedural timelines for service of notice, filing objections, and replies before the next hearing on 29.03.2023.

24
Stage 23Final Ruling Order

Tribunal Order #0901126003992023-24-01-2025

The Tribunal ruled that a promoter cannot use an out-of-court settlement to curtail an allottee's statutory right to receive delay interest under Section 18(1) of the RERA Act, 2016. Consequently, it set aside the Regulatory Authority's dismissal of the execution petition and ordered the restoration of proceedings to enforce the payment of interest.

25
Stage 24Interim Order

Tribunal Order #0901126003992023-07-05-2024

The Tribunal rejected the respondent's application for an extension of time due to procedural defects and ordered the President and Secretary of the respondent to appear on the next date to show cause why proceedings should not be initiated against them under Section 64 of the Act for non-compliance.

26
Stage 25Interim Order

Tribunal Order #0901126003992023-15-04-2024

The Tribunal granted the respondent one week to calculate and submit a statement detailing the total amount payable to the appellant under the order dated 10.04.2019, after accounting for payments already made during settlement.

27
Stage 26Interim Order

Tribunal Order #0901126003992023-08-08-2024

The Tribunal noted the respondent's failure to comply with previous orders and warned that the President and Secretary may face proceedings under Section 64 of the Act for non-compliance. The appellant was granted one week to provide details regarding the current office bearers of the respondent organization.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal ruled that a promoter cannot use an out-of-court settlement to curtail an allottee's statutory right to receive delay interest under Section 18(1) of the RERA Act, 2016. Consequently, it set aside the Regulatory Authority's dismissal of the execution petition and ordered the restoration of proceedings to enforce the payment of interest. Awarded in favor of Appellant. Awarded interest rate: MRLC+1%.

Disposal Winner: AppellantInterest Rate: MRLC+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal ruled that a promoter cannot use an out-of-court settlement to curtail an allottee's statutory right to receive delay interest under Section 18(1) of the RERA Act, 2016. Consequently, it set aside the Regulatory Authority's dismissal of the execution petition and ordered the restoration of proceedings to enforce the payment of interest.

Ruling Awarded To

Appellant

Awarded Interest Rate

MRLC+1%

Interest Period

till the handing over of the possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey
  • Isha Asthana

Respondent Advocate(s)

  • Amit Yadav
  • Raj Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126003992023-24-01-2025

The Tribunal ruled that a promoter cannot use an out-of-court settlement to curtail an allottee's statutory right to receive delay interest under Section 18(1) of the RERA Act, 2016. Consequently, it set aside the Regulatory Authority's dismissal of the execution petition and ordered the restoration of proceedings to enforce the payment of interest.

INTERIM_ORDEROrder ID: 0901126003992023-07-05-2024

The Tribunal rejected the respondent's application for an extension of time due to procedural defects and ordered the President and Secretary of the respondent to appear on the next date to show cause why proceedings should not be initiated against them under Section 64 of the Act for non-compliance.

INTERIM_ORDEROrder ID: 0901126003992023-15-04-2024

The Tribunal granted the respondent one week to calculate and submit a statement detailing the total amount payable to the appellant under the order dated 10.04.2019, after accounting for payments already made during settlement.

INTERIM_ORDEROrder ID: 0901126003992023-08-08-2024

The Tribunal noted the respondent's failure to comply with previous orders and warned that the President and Secretary may face proceedings under Section 64 of the Act for non-compliance. The appellant was granted one week to provide details regarding the current office bearers of the respondent organization.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ajpa parishad sehkari awas samiti ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →