up_reraStatus: Completed
CASE ID: 0901126003982019

Appellant / Complainant

U.P Avas Evam Vikas Parishad

VS

Respondent

Pradeep Kumar

Disputed Amount

1,00,06,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003982019 by U.P Avas Evam Vikas Parishad against Pradeep Kumar before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 114/09/2023

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed the appeals filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's orders for delayed possession and interest at MCLR+1%, and directed the transfer of pre-deposited funds to the Regulatory Authority for disbursement to the allottees.

3
Stage 213/09/2023

for delivery of Judgment/Order

No text available.

4
Stage 312/09/2023

for delivery of Judgment/Order

No text available.

5
Stage 423/08/2023

Hearing

The Tribunal heard arguments from the counsel for the applicant and the respondent, subsequently reserving judgment on the matter.

6
Stage 531/07/2023

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections regarding compliance with Section 43(5) of the Act and scheduled the next hearing for August 23, 2023.

7
Stage 606/07/2023

Hearing

The Tribunal directed the appellant's counsel to examine a calculation chart provided by the respondent regarding incomplete compliance with Section 43(5) of the Act and to rectify any deficiencies before the next hearing.

8
Stage 727/04/2023

Hearing

The Tribunal adjourned the matter due to lack of time and rescheduled the hearing for July 6, 2023.

9
Stage 817/03/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the case for hearing on 27.04.2023.

10
Stage 908/02/2023

Hearing

No text available.

11
Stage 1022/12/2022

Hearing

The Tribunal adjourned the matter due to lack of time and scheduled the appeal for a hearing on 08.02.2023.

12
Stage 1122/03/2021

Compliance of section 43(5)

No text available.

13
Stage 1223/02/2021

Further Order

The Tribunal adjourned the case due to the absence of both parties and rescheduled the hearing for 22.03.2021.

14
Stage 1309/02/2021

Further Order

The Tribunal granted the applicant permission to file a reply to documents submitted by the respondent regarding the incomplete status of the project and scheduled the matter for further orders on 23.03.2021.

15
Stage 1421/01/2021

Hearing

The Tribunal directed the respondent, Pradeep Kumar, to file supporting documents regarding the incomplete status of the project in a concise form at least three days before the next hearing.

16
Stage 1507/12/2020

Hearing

No text available.

17
Stage 16Final Ruling Order

Tribunal Order #0901126003982019-14-09-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeals filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's orders for delayed possession and interest at MCLR+1%, and directed the transfer of pre-deposited funds to the Regulatory Authority for disbursement to the allottees.

18
Stage 17Interim Order

Tribunal Order #0901126003982019-21-01-2021

The Tribunal directed the respondent, Pradeep Kumar, to file supporting documents regarding the incomplete status of the project in a concise form at least three days before the next hearing.

19
Stage 18Interim Order

Tribunal Order #0901126003982019-06-07-2023

The Tribunal directed the appellant's counsel to examine a calculation chart provided by the respondent regarding incomplete compliance with Section 43(5) of the Act and to rectify any deficiencies before the next hearing.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeals filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's orders for delayed possession and interest at MCLR+1%, and directed the transfer of pre-deposited funds to the Regulatory Authority for disbursement to the allottees. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeals filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's orders for delayed possession and interest at MCLR+1%, and directed the transfer of pre-deposited funds to the Regulatory Authority for disbursement to the allottees.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 23.01.2017 to 28.02.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vijay Pratap Singh Chauhan

Respondent Advocate(s)

  • Pradeep Kumar

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126003982019-14-09-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeals filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's orders for delayed possession and interest at MCLR+1%, and directed the transfer of pre-deposited funds to the Regulatory Authority for disbursement to the allottees.

INTERIM_ORDEROrder ID: 0901126003982019-21-01-2021

The Tribunal directed the respondent, Pradeep Kumar, to file supporting documents regarding the incomplete status of the project in a concise form at least three days before the next hearing.

INTERIM_ORDEROrder ID: 0901126003982019-06-07-2023

The Tribunal directed the appellant's counsel to examine a calculation chart provided by the respondent regarding incomplete compliance with Section 43(5) of the Act and to rectify any deficiencies before the next hearing.