CASE ID: 0901126003822019

Appellant / Complainant

Ifci Infrastructure Development Ltd.

VS

Respondent

Ram Dayal

Developer Firm

ifci infrastructure development ltd.

Disputed Amount

53,47,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

38 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003822019 by Ifci Infrastructure Development Ltd. against Ram Dayal before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 119/11/2024

Hearing

The Tribunal dismissed the appeal filed by M/S IFCI Infrastructure Development Ltd., upholding the RERA Authority's order for the payment of delay interest to the respondent and directing a computation of the surplus amount due after deducting the Rs. 87,000 already paid.

3
Stage 207/11/2024

Hearing

Upon the joint request of the counsel for both parties, the Tribunal has rescheduled the hearing of the appeal to 19.11.2024.

4
Stage 303/05/2023

Final Hearing

The appeal filed by M/S IFCI Infrastructure Development Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

5
Stage 422/03/2023

Final Hearing

No text available.

6
Stage 515/02/2023

Final Hearing

The Tribunal directed the respondent's counsel to correctly upload objections into the designated respondent's folder within one week and scheduled the appeal for hearing on 22.03.2023.

7
Stage 613/01/2023

Final Hearing

No text available.

8
Stage 712/12/2022

Final Hearing

No text available.

9
Stage 823/11/2022

Final Hearing

Upon the joint request of the counsels for both parties, the tribunal has adjourned the appeal and scheduled it for hearing on 12.12.2022.

10
Stage 919/11/2022

Final Hearing

The Tribunal adjourned the proceedings of Appeal-709/2021 following a request from the respondent's counsel due to a personal commitment. The matter is scheduled for hearing on 23.11.2022.

11
Stage 1007/11/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for a hearing on December 2, 2022.

12
Stage 1128/09/2022

Final Hearing

This text represents the header/caption of a court order from the U.P. Real Estate Appellate Tribunal regarding Appeal-709/2021 between M/S IFCI Infrastructure Development Ltd. and Ramdayal; however, no substantive ruling or directive is contained in this specific excerpt.

13
Stage 1209/09/2022

Final Hearing

No text available.

14
Stage 1317/08/2022

Final Hearing

The Tribunal granted a request for adjournment from the respondent's counsel due to urgent work and rescheduled the hearing for 09.09.2022.

15
Stage 1427/07/2022

Final Hearing

The Tribunal adjourned the proceedings due to the absence of the appellant's counsel and scheduled the appeal for a final hearing on 17.08.2022.

16
Stage 1519/05/2022

Final Hearing

The Tribunal directed the parties to exchange and submit lists of dates, events, and relied-upon judgments within 20 days and scheduled the next hearing for July 27, 2022.

17
Stage 1618/04/2022

Final Hearing

The Tribunal closed the final opportunity for the respondent to file a reply to the grounds of appeal and scheduled the case for hearing on 19.05.2022.

18
Stage 1725/02/2022

Final Hearing

The Tribunal granted the respondent a final opportunity to file objections to the grounds of appeal within 15 days and scheduled the next hearing for April 18, 2022.

19
Stage 1817/01/2022

Final Hearing

No text available.

20
Stage 1922/12/2021

Final Hearing

The Tribunal directed the respondent to file objections to the grounds of appeal and serve a copy to the appellant via email, scheduling the next hearing for 17.01.2022.

21
Stage 2001/12/2021

Final Hearing

The Tribunal directed the respondent to file objections to the grounds of appeal and serve a copy to the appellant via email, with the matter listed for further orders on 22.12.2021.

22
Stage 2111/11/2021

Hearing

The Tribunal granted a 10-day extension to the respondent for filing objections to the grounds of appeal and directed the parties to exchange replies via email and upload documents to the e-portal before the next hearing on 01.12.2021.

23
Stage 2221/10/2021

Hearing

No text available.

24
Stage 2305/10/2021

Hearing

The Tribunal condoned a one-day delay in filing the appeal and converted the defective application into a Regular Appeal, ruling that the time taken to pursue a rectification application can be excluded when calculating limitation.

25
Stage 2401/10/2021

Delay condonation

The Tribunal granted the appellant's counsel three days to prepare submissions regarding the respondent's objections and adjourned the matter to 05.10.2021.

26
Stage 2529/09/2021

Delay condonation

The Tribunal granted a request from the counsel for both parties to adjourn the matter and list the case on 21.10.2021.

27
Stage 2615/04/2021

Delay condonation

No text available.

28
Stage 2725/03/2021

Delay condonation

The Tribunal directed the Registry to summon the records of Complaint No. 120186279 from RERA to verify whether the rectification application was filed by the applicant or respondent to determine the validity of the limitation period.

29
Stage 2803/03/2021

Delay condonation

The Tribunal directed the registry to record Shri Anurag Arora as counsel for the applicant and scheduled the case for hearing on the application for condonation of delay on 25.03.2021.

30
Stage 2908/02/2021

For Order

The Tribunal adjourned the matter due to a request from the respondent's counsel and directed both parties to exchange objections and replies via email and upload them to the e-portal before the next hearing on 03.03.2021.

31
Stage 3022/01/2021

Delay condonation

No text available.

32
Stage 3105/01/2021

Hearing

No text available.

33
Stage 3203/12/2020

Hearing

No text available.

34
Stage 33Final Ruling Order

Tribunal Order #0901126003822019-19-11-2024

The Tribunal dismissed the appeal filed by M/S IFCI Infrastructure Development Ltd., upholding the RERA Authority's order for the payment of delay interest to the respondent and directing a computation of the surplus amount due after deducting the Rs. 87,000 already paid.

35
Stage 34Final Ruling Order

Tribunal Order #0901126003822019-03-05-2023

The appeal filed by M/S IFCI Infrastructure Development Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

36
Stage 35Interim Order

Tribunal Order #0901126003822019-05-10-2021

The Tribunal condoned a one-day delay in filing the appeal and converted the defective application into a Regular Appeal, ruling that the time taken to pursue a rectification application can be excluded when calculating limitation.

37
Stage 36Interim Order

Tribunal Order #0901126003822019-25-03-2021

The Tribunal directed the Registry to summon the records of Complaint No. 120186279 from RERA to verify whether the rectification application was filed by the applicant or respondent to determine the validity of the limitation period.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by M/S IFCI Infrastructure Development Ltd., upholding the RERA Authority's order for the payment of delay interest to the respondent and directing a computation of the surplus amount due after deducting the Rs. 87,000 already paid. The appeal filed by M/S IFCI Infrastructure Development Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel. Awarded in favor of Respondent. Awarded interest rate: MCLR+01 percent.

Disposal Winner: RespondentInterest Rate: MCLR+01 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by M/S IFCI Infrastructure Development Ltd., upholding the RERA Authority's order for the payment of delay interest to the respondent and directing a computation of the surplus amount due after deducting the Rs. 87,000 already paid. The appeal filed by M/S IFCI Infrastructure Development Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+01 percent

Interest Period

till the date of possession of the Unit (23.06.2018)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Arora

Respondent Advocate(s)

  • Saghar Mehdi

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126003822019-19-11-2024

The Tribunal dismissed the appeal filed by M/S IFCI Infrastructure Development Ltd., upholding the RERA Authority's order for the payment of delay interest to the respondent and directing a computation of the surplus amount due after deducting the Rs. 87,000 already paid.

FINAL_ORDEROrder ID: 0901126003822019-03-05-2023

The appeal filed by M/S IFCI Infrastructure Development Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

INTERIM_ORDEROrder ID: 0901126003822019-05-10-2021

The Tribunal condoned a one-day delay in filing the appeal and converted the defective application into a Regular Appeal, ruling that the time taken to pursue a rectification application can be excluded when calculating limitation.

INTERIM_ORDEROrder ID: 0901126003822019-25-03-2021

The Tribunal directed the Registry to summon the records of Complaint No. 120186279 from RERA to verify whether the rectification application was filed by the applicant or respondent to determine the validity of the limitation period.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ifci infrastructure development ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →