up_reraStatus: Completed
CASE ID: 0901126003792019

Appellant / Complainant

Neeraj Rai

VS

Respondent

U.P. Avas Evam Vikas Parishad

Disputed Amount

34,80,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003792019 by Neeraj Rai against U.P. Avas Evam Vikas Parishad before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility Disputes
2
Stage 128/09/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Neeraj Rai, upholding the Regulatory Authority's order that directed the promoter to deliver possession and execute the sale deed while paying interest for the delayed period at MCLR+1%.

3
Stage 223/08/2022

Hearing

The court heard arguments from both parties regarding Appeal-189/2019 and reserved the judgment for later delivery.

4
Stage 302/08/2022

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the appeal for hearing on 23.08.2022.

5
Stage 420/07/2022

Hearing

The Tribunal granted the appellant one week's extension to file a reply to the respondent's objections and scheduled the next hearing for August 2, 2022.

6
Stage 512/07/2022

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the next hearing for July 20, 2022.

7
Stage 623/05/2022

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and directed that the reply be shared via email and uploaded to the e-portal before the next hearing on 12.07.2022.

8
Stage 719/04/2022

Hearing

The Tribunal directed the respondent to download the amended appeal from the e-portal and provided 15 days to file a reply regarding the amendment.

9
Stage 802/03/2022

Final Hearing

The Tribunal noted the appellant's amendment to the appeal and directed the respondent to file a reply to the grounds of appeal by the next hearing date on 19.04.2022.

10
Stage 919/01/2022

Final Hearing

No text available.

11
Stage 1003/01/2022

Final Hearing

The Tribunal noted that the appellant's counsel could not connect for a requested virtual hearing due to poor connectivity and has rescheduled the appeal for hearing on 19.01.2022.

12
Stage 1121/12/2021

Final Hearing

The Tribunal directed the appellant to provide an amended memo of appeal to the respondent and scheduled the matter for further orders on 03.01.2022.

13
Stage 1207/12/2021

Final Hearing

The Tribunal allowed the appellant's application to amend the memo of appeal by adding new grounds and deleting a prayer for harassment costs, while setting a timeline for filing objections and amended documents.

14
Stage 1318/11/2021

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and directed both parties to exchange pleadings before the next hearing scheduled for 07.12.2021.

15
Stage 1427/10/2021

Hearing

The Tribunal granted a joint request from the counsels of both parties to reschedule the hearing of Appeal-189/2019 to 18.11.2021.

16
Stage 1527/09/2021

Hearing

The Tribunal granted a request from both counsels to adjourn the matter, rescheduling the appeal for hearing on 27.10.2021.

17
Stage 1613/04/2021

Hearing

No text available.

18
Stage 1722/03/2021

Hearing

No text available.

19
Stage 1802/03/2021

Hearing

The court adjourned the appeal to 22.03.2021 due to lawyers abstaining from work in support of a call by the Oudh Bar Association.

20
Stage 1909/02/2021

For Order

The Tribunal granted an adjournment request made by the appellant's counsel due to illness and rescheduled the hearing for March 2, 2021.

21
Stage 2022/01/2021

For Order

The Tribunal has adjourned the appeal to 09.02.2021 following a joint request from the counsels for both parties.

22
Stage 2105/01/2021

Final Hearing

No text available.

23
Stage 2211/12/2020

Final Hearing

No text available.

24
Stage 23Final Ruling Order

Tribunal Order #0901126003792019-28-09-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Neeraj Rai, upholding the Regulatory Authority's order that directed the promoter to deliver possession and execute the sale deed while paying interest for the delayed period at MCLR+1%.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Neeraj Rai, upholding the Regulatory Authority's order that directed the promoter to deliver possession and execute the sale deed while paying interest for the delayed period at MCLR+1%. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Neeraj Rai, upholding the Regulatory Authority's order that directed the promoter to deliver possession and execute the sale deed while paying interest for the delayed period at MCLR+1%.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 26.03.2016 till the date of actual delivery of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 14(3)Section 12Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saghar Mehdi

Respondent Advocate(s)

  • N N Pandey

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126003792019-28-09-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Neeraj Rai, upholding the Regulatory Authority's order that directed the promoter to deliver possession and execute the sale deed while paying interest for the delayed period at MCLR+1%.