Appellant / Complainant
Pawan Kumar Kushwaha
Respondent
Paramount Propbuild Pvt. Ltd
paramount propbuild pvt. ltd
₹18,14,663
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126003642022 by Pawan Kumar Kushwaha against Paramount Propbuild Pvt. Ltd before up_rera.
for delivery of Judgment/Order
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest from the promised possession date until actual legal possession (after obtaining OC/CC) and to bear the cost of stamp duty as per their prior written commitment.
Further Hearing
The Tribunal heard arguments regarding the appellant's challenge to a RERA order concerning interest rates for delayed possession and the validity of offering possession without an Occupancy Certificate (OC/CC). The judgment has been reserved following discussions on deeming provisions and stamp duty expenditures.
Further Hearing
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for 27.07.2022.
Further Hearing
The Tribunal directed the respondent to execute the sub-lease deed upon the applicant's request and payment of necessary charges, while also adjourning the matter to 15.07.2022.
Further Hearing
The Tribunal granted the appellant's counsel 24 hours to seek instructions and adjourned the matter to May 24, 2022.
Further Hearing
The Tribunal directed the respondent to produce a detailed bifurcation of the Rs. 17,00,688/- demand raised against the applicant and ordered compliance with previous orders dated 04.05.2022 and 06.05.2022.
Further Hearing
The Tribunal adjourned the defective appeal to 16.05.2022 at the request of the respondent's counsel to allow for compliance with previous orders.
Further Hearing
The Respondent (M/S Paramount Propbuild Pvt. Ltd) proposed to waive holding charges, one year of maintenance, stamp fees for the conveyance deed, and delay interest; the Tribunal directed the Respondent to formally present this offer on 11.05.2022.
Delay condonation
The Tribunal granted the respondent's counsel two days to seek instructions regarding disputed stamp fees and advance maintenance charges, adjourning the matter to 06.05.2022.
Delay condonation
The Tribunal granted the respondent two days to seek instructions regarding the status of the Occupancy Certificate/Completion Certificate (OC/CC) and scheduled the matter for 04.05.2022 to consider the application for condonation of delay.
Delay condonation
The Tribunal directed the respondent to file objections within three days and the appellant to reply within a week via email, scheduling the matter for May 2, 2022, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the applicant to reply. The matter is scheduled for hearing on 18.04.2022.
Defect Removal
The Tribunal rejected the application for exemption from filing a certified copy of the impugned order but granted the appellant 15 days to file it, while simultaneously issuing notice to the respondent and setting procedural timelines for service and pleadings.
Tribunal Order #0901126003642022-29-09-2022
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest from the promised possession date until actual legal possession (after obtaining OC/CC) and to bear the cost of stamp duty as per their prior written commitment.
Tribunal Order #0901126003642022-27-07-2022
The Tribunal heard arguments regarding the appellant's challenge to a RERA order concerning interest rates for delayed possession and the validity of offering possession without an Occupancy Certificate (OC/CC). The judgment has been reserved following discussions on deeming provisions and stamp duty expenditures.
Tribunal Order #0901126003642022-24-05-2022
The Tribunal directed the respondent to execute the sub-lease deed upon the applicant's request and payment of necessary charges, while also adjourning the matter to 15.07.2022.
Tribunal Order #0901126003642022-06-05-2022
The Respondent (M/S Paramount Propbuild Pvt. Ltd) proposed to waive holding charges, one year of maintenance, stamp fees for the conveyance deed, and delay interest; the Tribunal directed the Respondent to formally present this offer on 11.05.2022.
Tribunal Order #0901126003642022-16-05-2022
The Tribunal directed the respondent to produce a detailed bifurcation of the Rs. 17,00,688/- demand raised against the applicant and ordered compliance with previous orders dated 04.05.2022 and 06.05.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest from the promised possession date until actual legal possession (after obtaining OC/CC) and to bear the cost of stamp duty as per their prior written commitment. Awarded in favor of Partial. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest from the promised possession date until actual legal possession (after obtaining OC/CC) and to bear the cost of stamp duty as per their prior written commitment.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR + 1%
Interest Period
from the date of handing over possession as per agreement till legal handing over of possession after obtaining occupancy certificate and completion certificate
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Abhishek Khare
- Aahuti Agarwal
Respondent Advocate(s)
- Saurabh Misra
Official RERA Tribunal Orders (5)
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest from the promised possession date until actual legal possession (after obtaining OC/CC) and to bear the cost of stamp duty as per their prior written commitment.
The Tribunal heard arguments regarding the appellant's challenge to a RERA order concerning interest rates for delayed possession and the validity of offering possession without an Occupancy Certificate (OC/CC). The judgment has been reserved following discussions on deeming provisions and stamp duty expenditures.
The Tribunal directed the respondent to execute the sub-lease deed upon the applicant's request and payment of necessary charges, while also adjourning the matter to 15.07.2022.
The Respondent (M/S Paramount Propbuild Pvt. Ltd) proposed to waive holding charges, one year of maintenance, stamp fees for the conveyance deed, and delay interest; the Tribunal directed the Respondent to formally present this offer on 11.05.2022.
The Tribunal directed the respondent to produce a detailed bifurcation of the Rs. 17,00,688/- demand raised against the applicant and ordered compliance with previous orders dated 04.05.2022 and 06.05.2022.
Need to research all rulings for paramount propbuild pvt. ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.