up_reraStatus: Completed
CASE ID: 0901126003562019

Appellant / Complainant

Vipul Jain

VS

Respondent

Vasu Infrastructure Pvt. Ltd.

Developer Firm

vasu infrastructure pvt. ltd.

Disputed Amount

33,02,896

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

37 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003562019 by Vipul Jain against Vasu Infrastructure Pvt. Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 129/05/2023

for delivery of Judgment/Order

The Tribunal partially allowed the appeal, modifying the previous order to grant the appellant interest for delay in possession from the promised date of 07.05.2016 until the legal offer of possession on 18.02.2021 at a rate of MCLR+1%.

3
Stage 225/05/2023

for delivery of Judgment/Order

No text available.

4
Stage 325/11/2022

Further Hearing

The Tribunal heard arguments regarding maintenance charge calculations and the validity of possession offers, subsequently reserving judgment on the appeal.

5
Stage 424/11/2022

Further Hearing

The Tribunal directed the respondent to clarify when the offer of possession was made and to provide a statement regarding the formation of the association and the handing over of common areas. The matter is scheduled for further hearing on 25.11.2022.

6
Stage 519/11/2022

Final Hearing

The Tribunal recorded that no time was left during the session and ordered the matter to be listed for hearing on 24.11.2022.

7
Stage 618/10/2022

For Order

The Tribunal has scheduled the appeal for a hearing on November 23, 2022, noting that pleadings have been exchanged and the matter is ripe for hearing.

8
Stage 723/09/2022

Hearing

The Tribunal granted the respondent one week to file objections to the amended memo of appeal and directed the parties to exchange replies via email and upload them to the e-portal before the next hearing on 18.10.2022.

9
Stage 831/08/2022

Hearing on Amendment Application

The Tribunal allowed the appellant's application to amend the appeal by adding new legal grounds, directing the appellant to incorporate these changes in red ink and file an amended copy within a week.

10
Stage 916/08/2022

For Order

The Respondent's counsel requested and was granted a 10-day extension to file objections to the proposed amendment in the memo of appeal, with the matter scheduled for hearing on 31.08.2022.

11
Stage 1002/08/2022

Final Hearing

The Tribunal issued a show-cause notice to the Respondent's CMD for violating a previous RERA order by calculating delay interest based on the Builder Buyer Agreement instead of the mandated MCLR+1%, and directed the filing of a personal affidavit from the CMD.

12
Stage 1114/07/2022

Final Hearing

The Tribunal granted a request for final hearing and scheduled the appeal for further proceedings on 02.08.2022.

13
Stage 1207/07/2022

Final Hearing

The Tribunal granted the respondent one week to comply with a previous order dated 18.05.2022, warning that failure to do so will require the Managing Director to appear in person to show cause why proceedings should not be initiated under Section 64 of the Act.

14
Stage 1318/05/2022

Final Hearing

The Tribunal directed the Respondent to issue a fresh demand letter consistent with the Regulatory Authority's order within 15 days, and ordered both parties to exchange details regarding the amounts receivable or payable as per RERA directions.

15
Stage 1413/04/2022

Final Hearing

The Tribunal adjourned the appeal due to the absence of counsel and issued a directive that any future requests for adjournment must be made through a formal application.

16
Stage 1524/02/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to sanctioned leave and rescheduled the hearing for 13.04.2022.

17
Stage 1613/01/2022

Final Hearing

No text available.

18
Stage 1724/12/2021

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 13.01.2022.

19
Stage 1810/12/2021

Final Hearing

The Tribunal noted that the rejoinder has been filed and directed both parties to prepare and exchange a list of dates and events before the next hearing.

20
Stage 1929/11/2021

Final Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the final hearing for December 10, 2021.

21
Stage 2011/11/2021

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his unavailability and rescheduled the appeal for a final hearing on 29.11.2021.

22
Stage 2128/10/2021

Hearing

No text available.

23
Stage 2216/09/2021

Hearing

The Tribunal directed the parties to exchange lists of dates, events, and relied-upon judgments/orders before the next hearing scheduled for 28.10.2021.

24
Stage 2316/04/2021

Hearing

No text available.

25
Stage 2422/03/2021

Further Order

The Tribunal directed the respondent to file a reply to the grounds of appeal within three days and noted the appellant's request for an offer of possession following necessary financial adjustments.

26
Stage 2523/02/2021

Further Order

The Tribunal granted an adjournment requested by the respondent due to the injury of the Builder Company's Director and rescheduled the hearing for 22.03.2021.

27
Stage 2618/01/2021

Hearing on Appeal

No text available.

28
Stage 2712/12/2020

Hearing on Appeal

No text available.

29
Stage 28Interim Order

Tribunal Order #0901126003562019-24-11-2022

The Tribunal directed the respondent to clarify when the offer of possession was made and to provide a statement regarding the formation of the association and the handing over of common areas. The matter is scheduled for further hearing on 25.11.2022.

30
Stage 29Interim Order

Tribunal Order #0901126003562019-31-08-2022

The Tribunal allowed the appellant's application to amend the appeal by adding new legal grounds, directing the appellant to incorporate these changes in red ink and file an amended copy within a week.

31
Stage 30Interim Order

Tribunal Order #0901126003562019-02-08-2022

The Tribunal issued a show-cause notice to the Respondent's CMD for violating a previous RERA order by calculating delay interest based on the Builder Buyer Agreement instead of the mandated MCLR+1%, and directed the filing of a personal affidavit from the CMD.

32
Stage 31Interim Order

Tribunal Order #0901126003562019-18-05-2022

The Tribunal directed the Respondent to issue a fresh demand letter consistent with the Regulatory Authority's order within 15 days, and ordered both parties to exchange details regarding the amounts receivable or payable as per RERA directions.

33
Stage 32Interim Order

Tribunal Order #0901126003562019-22-03-2021

The Tribunal directed the respondent to file a reply to the grounds of appeal within three days and noted the appellant's request for an offer of possession following necessary financial adjustments.

34
Stage 33Final Ruling Order

Tribunal Order #0901126003562019-29-05-2023

The Tribunal partially allowed the appeal, modifying the previous order to grant the appellant interest for delay in possession from the promised date of 07.05.2016 until the legal offer of possession on 18.02.2021 at a rate of MCLR+1%.

35
Stage 34Interim Order

Tribunal Order #0901126003562019-25-11-2022

The Tribunal heard arguments regarding maintenance charge calculations and the validity of possession offers, subsequently reserving judgment on the appeal.

36
Stage 35Interim Order

Tribunal Order #0901126003562019-07-07-2022

The Tribunal granted the respondent one week to comply with a previous order dated 18.05.2022, warning that failure to do so will require the Managing Director to appear in person to show cause why proceedings should not be initiated under Section 64 of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the appeal, modifying the previous order to grant the appellant interest for delay in possession from the promised date of 07.05.2016 until the legal offer of possession on 18.02.2021 at a rate of MCLR+1%. Awarded in favor of Partial. Awarded interest rate: MCLR + 1%.

Disposal Winner: PartialInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the appeal, modifying the previous order to grant the appellant interest for delay in possession from the promised date of 07.05.2016 until the legal offer of possession on 18.02.2021 at a rate of MCLR+1%.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1%

Interest Period

from 07.05.2016 till 18.02.2021

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey

Respondent Advocate(s)

  • Himanshu Hemant Gupta
  • Ashivini Dwivedi

Official RERA Tribunal Orders (8)

INTERIM_ORDEROrder ID: 0901126003562019-24-11-2022

The Tribunal directed the respondent to clarify when the offer of possession was made and to provide a statement regarding the formation of the association and the handing over of common areas. The matter is scheduled for further hearing on 25.11.2022.

INTERIM_ORDEROrder ID: 0901126003562019-31-08-2022

The Tribunal allowed the appellant's application to amend the appeal by adding new legal grounds, directing the appellant to incorporate these changes in red ink and file an amended copy within a week.

INTERIM_ORDEROrder ID: 0901126003562019-02-08-2022

The Tribunal issued a show-cause notice to the Respondent's CMD for violating a previous RERA order by calculating delay interest based on the Builder Buyer Agreement instead of the mandated MCLR+1%, and directed the filing of a personal affidavit from the CMD.

INTERIM_ORDEROrder ID: 0901126003562019-18-05-2022

The Tribunal directed the Respondent to issue a fresh demand letter consistent with the Regulatory Authority's order within 15 days, and ordered both parties to exchange details regarding the amounts receivable or payable as per RERA directions.

INTERIM_ORDEROrder ID: 0901126003562019-22-03-2021

The Tribunal directed the respondent to file a reply to the grounds of appeal within three days and noted the appellant's request for an offer of possession following necessary financial adjustments.

FINAL_ORDEROrder ID: 0901126003562019-29-05-2023

The Tribunal partially allowed the appeal, modifying the previous order to grant the appellant interest for delay in possession from the promised date of 07.05.2016 until the legal offer of possession on 18.02.2021 at a rate of MCLR+1%.

INTERIM_ORDEROrder ID: 0901126003562019-25-11-2022

The Tribunal heard arguments regarding maintenance charge calculations and the validity of possession offers, subsequently reserving judgment on the appeal.

INTERIM_ORDEROrder ID: 0901126003562019-07-07-2022

The Tribunal granted the respondent one week to comply with a previous order dated 18.05.2022, warning that failure to do so will require the Managing Director to appear in person to show cause why proceedings should not be initiated under Section 64 of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for vasu infrastructure pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →