up_reraStatus: Completed
CASE ID: 0901126003212019

Appellant / Complainant

Ahmad Haris Jamil

VS

Respondent

Grahlaxmi Sahkari Awas Samiti Ltd.

Developer Firm

grahlaxmi sahkari awas samiti ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003212019 by Ahmad Haris Jamil against Grahlaxmi Sahkari Awas Samiti Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability
2
Stage 102/08/2022

Final Hearing

The Tribunal dismissed the appeal as not maintainable because the respondent's project was not registered with RERA, citing Supreme Court precedent regarding the retroactive application of the Act to ongoing projects.

3
Stage 226/07/2022

Final Hearing

The Tribunal adjourned the appeal due to the absence of the respondent's counsel and rescheduled the hearing for August 2, 2022.

4
Stage 318/05/2022

Final Hearing

The Tribunal directed the respondent to file written arguments along with relied-upon judgments and scheduled the matter for hearing on 26.07.2022.

5
Stage 413/04/2022

Final Hearing

The Tribunal directed both parties to file and exchange written submissions along with relied-upon judgments within 20 days and scheduled the matter for hearing on 17.05.2022.

6
Stage 524/02/2022

Final Hearing

The Tribunal adjourned the case due to the absence of both parties and rescheduled the hearing for April 13, 2022.

7
Stage 613/01/2022

Final Hearing

No text available.

8
Stage 703/01/2022

Final Hearing

The Tribunal directed the respondent to clarify the legality of PLC charges and ensure escalation charges do not exceed 5%, with instructions to revise any discrepancies in the final demand and submit it to the appellant.

9
Stage 821/12/2021

Final Hearing

The Tribunal noted the respondent's compliance with a previous order and directed the appellant to file a response to the papers submitted by the respondent. The matter is scheduled for further orders on 03.01.2022.

10
Stage 901/12/2021

Final Hearing

The Tribunal directed the respondent's counsel to comply with a previous order dated 15.11.2021 and scheduled the appeal for further orders on 21.12.2021.

11
Stage 1015/11/2021

Final Hearing

The Tribunal granted the respondent a one-week extension to comply with a previous order regarding the rectification of dues, noting that failure to comply would require the President of the respondent organization to appear personally.

12
Stage 1128/10/2021

Hearing

The Tribunal allowed the appellant's application to amend the prayer clause and directed the respondent to examine discrepancies regarding interest calculations, amenity charges, and unauthorized PLC charges for rectification.

13
Stage 1201/10/2021

Hearing

The Tribunal granted the appellant permission to file an amendment application for the prayer clause and directed both parties to exchange proposed amendments and objections via email before the next hearing on 28.10.2020.

14
Stage 1313/09/2021

Hearing

The Tribunal granted parties time to exchange documents and objections via email and e-portal, scheduling the next hearing for October 1, 2021.

15
Stage 1429/04/2021

Hearing

No text available.

16
Stage 1506/04/2021

Hearing

No text available.

17
Stage 1616/03/2021

For Order

The Tribunal granted a one-week extension to the appellant's counsel to ensure compliance with a previous order dated 21.01.2021 and scheduled the next hearing for 06.04.2021.

18
Stage 1723/02/2021

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and scheduled the appeal for hearing on 16.03.2021.

19
Stage 1812/02/2021

For Order

The Tribunal granted the respondent a one-week extension to file a response regarding a previous query and scheduled the next hearing for 23.02.2021.

20
Stage 1921/01/2021

Further Order

The Tribunal directed the respondent to file records regarding actions taken following a previous Regulatory Authority order, including details of demands against the appellant and adjustments for project delays.

21
Stage 2016/12/2020

Further Order

No text available.

22
Stage 21Final Ruling Order

Tribunal Order #0901126003212019-02-08-2022

The Tribunal dismissed the appeal as not maintainable because the respondent's project was not registered with RERA, citing Supreme Court precedent regarding the retroactive application of the Act to ongoing projects.

23
Stage 22Interim Order

Tribunal Order #0901126003212019-28-10-2021

The Tribunal allowed the appellant's application to amend the prayer clause and directed the respondent to examine discrepancies regarding interest calculations, amenity charges, and unauthorized PLC charges for rectification.

24
Stage 23Interim Order

Tribunal Order #0901126003212019-21-01-2021

The Tribunal directed the respondent to file records regarding actions taken following a previous Regulatory Authority order, including details of demands against the appellant and adjustments for project delays.

25
Stage 24Interim Order

Tribunal Order #0901126003212019-03-01-2022

The Tribunal directed the respondent to clarify the legality of PLC charges and ensure escalation charges do not exceed 5%, with instructions to revise any discrepancies in the final demand and submit it to the appellant.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal as not maintainable because the respondent's project was not registered with RERA, citing Supreme Court precedent regarding the retroactive application of the Act to ongoing projects. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal as not maintainable because the respondent's project was not registered with RERA, citing Supreme Court precedent regarding the retroactive application of the Act to ongoing projects.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

delay up to 30.04.2016 and thereafter from 01.05.2016 till receipt of the Occupancy Certificate

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ali Jibran

Respondent Advocate(s)

  • Shailender Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126003212019-02-08-2022

The Tribunal dismissed the appeal as not maintainable because the respondent's project was not registered with RERA, citing Supreme Court precedent regarding the retroactive application of the Act to ongoing projects.

INTERIM_ORDEROrder ID: 0901126003212019-28-10-2021

The Tribunal allowed the appellant's application to amend the prayer clause and directed the respondent to examine discrepancies regarding interest calculations, amenity charges, and unauthorized PLC charges for rectification.

INTERIM_ORDEROrder ID: 0901126003212019-21-01-2021

The Tribunal directed the respondent to file records regarding actions taken following a previous Regulatory Authority order, including details of demands against the appellant and adjustments for project delays.

INTERIM_ORDEROrder ID: 0901126003212019-03-01-2022

The Tribunal directed the respondent to clarify the legality of PLC charges and ensure escalation charges do not exceed 5%, with instructions to revise any discrepancies in the final demand and submit it to the appellant.

TathyaGrid RERA Intelligence AI

Need to research all rulings for grahlaxmi sahkari awas samiti ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →