Appellant / Complainant
Kunveer Jeet Singh
Respondent
M.K.S. Infratech Pvt. Ltd.
m.k.s. infratech pvt. ltd.
₹92,16,760
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126003192019 by Kunveer Jeet Singh against M.K.S. Infratech Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal set aside the Regulatory Authority's order directing possession and instead ruled that the appellant is entitled to a full refund of the deposited amount plus interest at the rate of MCLR+1% from the date of deposit until actual refund due to project delays.
Hearing
The appellant is challenging a Regulatory Authority order regarding a delay in possession, seeking a refund instead of the directed possession due to the respondent's failure to meet the timeline specified in the Allotment Letter.
Hearing
The Tribunal heard arguments regarding the appellant's claim for a refund with interest due to a three-year delay in possession by the respondent, and has reserved judgment on the matter.
Hearing
The Tribunal noted the appellant's request to file a Vakalatnama and recorded that no settlement could be reached between the parties, subsequently adjourning the matter to 31.08.2022 for hearing.
Hearing
The parties reported that settlement negotiations failed; consequently, the matter is scheduled for a hearing on its merits on 02.08.2022.
Hearing
The Tribunal noted that the parties are likely to reach an out-of-court settlement and directed the appellant in person and the respondent's representative to appear on the next hearing date of 26.05.2022.
Hearing
The appeal was dismissed for want of prosecution due to the non-appearance of the appellant and no request for adjournment.
Hearing
The Tribunal directed the appellant's counsel to serve additional documents filed on 01.03.2021 to the respondent via email and permitted the respondent to file a reply within one week thereafter.
Hearing
The Tribunal granted the appellant three days to file documents regarding the respondent's communication on refunds and scheduled the next hearing for April 2, 2021.
Final Hearing
The Tribunal directed the Registry to convert the matter into a Regular Appeal and granted a one-week extension for the deposition of costs previously imposed on 07.01.2021.
Hearing
The Tribunal allowed the application for condonation of an 8-day delay in filing the appeal, subject to a cost of Rs. 5,000/- to be used for library books, and scheduled the regular appeal for hearing on 28.01.2021.
Tribunal Order #0901126003192019-30-05-2023
The Tribunal set aside the Regulatory Authority's order directing possession and instead ruled that the appellant is entitled to a full refund of the deposited amount plus interest at the rate of MCLR+1% from the date of deposit until actual refund due to project delays.
Tribunal Order #0901126003192019-27-04-2023
The appellant is challenging a Regulatory Authority order regarding a delay in possession, seeking a refund instead of the directed possession due to the respondent's failure to meet the timeline specified in the Allotment Letter.
Tribunal Order #0901126003192019-28-01-2021
The Tribunal directed the Registry to convert the matter into a Regular Appeal and granted a one-week extension for the deposition of costs previously imposed on 07.01.2021.
Tribunal Order #0901126003192019-31-08-2022
The Tribunal heard arguments regarding the appellant's claim for a refund with interest due to a three-year delay in possession by the respondent, and has reserved judgment on the matter.
Tribunal Order #0901126003192019-07-01-2021
The Tribunal allowed the application for condonation of an 8-day delay in filing the appeal, subject to a cost of Rs. 5,000/- to be used for library books, and scheduled the regular appeal for hearing on 28.01.2021.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order directing possession and instead ruled that the appellant is entitled to a full refund of the deposited amount plus interest at the rate of MCLR+1% from the date of deposit until actual refund due to project delays. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order directing possession and instead ruled that the appellant is entitled to a full refund of the deposited amount plus interest at the rate of MCLR+1% from the date of deposit until actual refund due to project delays.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
from the date of deposit till the date of actual refund
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kushagra Dikshit
Respondent Advocate(s)
- Vivek Kumar Shukla
Official RERA Tribunal Orders (5)
The Tribunal set aside the Regulatory Authority's order directing possession and instead ruled that the appellant is entitled to a full refund of the deposited amount plus interest at the rate of MCLR+1% from the date of deposit until actual refund due to project delays.
The appellant is challenging a Regulatory Authority order regarding a delay in possession, seeking a refund instead of the directed possession due to the respondent's failure to meet the timeline specified in the Allotment Letter.
The Tribunal directed the Registry to convert the matter into a Regular Appeal and granted a one-week extension for the deposition of costs previously imposed on 07.01.2021.
The Tribunal heard arguments regarding the appellant's claim for a refund with interest due to a three-year delay in possession by the respondent, and has reserved judgment on the matter.
The Tribunal allowed the application for condonation of an 8-day delay in filing the appeal, subject to a cost of Rs. 5,000/- to be used for library books, and scheduled the regular appeal for hearing on 28.01.2021.
Need to research all rulings for m.k.s. infratech pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.