up_reraStatus: Completed
CASE ID: 0901126003162023

Appellant / Complainant

U.P. State Industrial Development Corporation Limited

VS

Respondent

Sapna Singh

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003162023 by U.P. State Industrial Development Corporation Limited against Sapna Singh before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing that the pre-deposited funds be transferred to U.P. RERA for distribution to allottees.

3
Stage 225/01/2024

For Order

The Tribunal has reserved its judgment regarding the appeal filed by U.P. State Industrial Development Corporation Limited against Sapna Singh.

4
Stage 308/01/2024

For Order

The Tribunal issued notice to the respondent to file objections within 10 days and scheduled the appeal for hearing on 25.01.2024 following a High Court remand.

5
Stage 419/07/2023

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 146/2023) via an order dated July 19, 2023.

6
Stage 505/05/2023

Delay condonation

The Tribunal deemed service of notice on the respondent sufficient based on postal and email delivery and granted the respondent 10 days to file objections.

7
Stage 620/04/2023

Delay condonation

The Tribunal granted the appellant's counsel one week to file an affidavit of service and scheduled the defective appeal for further orders on May 5, 2023.

8
Stage 713/03/2023

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of delay and noted that the appellant has deposited Rs. 10,75,998/- in compliance with Section 43(5) of the Act.

9
Stage 8Final Ruling Order

Tribunal Order #0901126003162023-07-05-2024

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing that the pre-deposited funds be transferred to U.P. RERA for distribution to allottees.

10
Stage 9Final Ruling Order

Tribunal Order #0901126003162023-19-07-2023

The U.P. Real Estate Appellate Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 146/2023) via an order dated July 19, 2023.

11
Stage 10Interim Order

Tribunal Order #0901126003162023-13-03-2023

The Tribunal issued notice to the respondent regarding an application for condonation of delay and noted that the appellant has deposited Rs. 10,75,998/- in compliance with Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing that the pre-deposited funds be transferred to U.P. RERA for distribution to allottees. The U.P. Real Estate Appellate Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 146/2023) via an order dated July 19, 2023. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing that the pre-deposited funds be transferred to U.P. RERA for distribution to allottees. The U.P. Real Estate Appellate Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 146/2023) via an order dated July 19, 2023.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from December 2016 till receipt of OC/CC or the date of offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey
  • Ramesh Chandra Mishra

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126003162023-07-05-2024

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing that the pre-deposited funds be transferred to U.P. RERA for distribution to allottees.

FINAL_ORDEROrder ID: 0901126003162023-19-07-2023

The U.P. Real Estate Appellate Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 146/2023) via an order dated July 19, 2023.

INTERIM_ORDEROrder ID: 0901126003162023-13-03-2023

The Tribunal issued notice to the respondent regarding an application for condonation of delay and noted that the appellant has deposited Rs. 10,75,998/- in compliance with Section 43(5) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →