up_reraStatus: Completed
CASE ID: 0901126003072019

Appellant / Complainant

Nomani Sadul Haque

VS

Respondent

Parsvnath Developers Ltd.

Developer Firm

parsvnath developers ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003072019 by Nomani Sadul Haque against Parsvnath Developers Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 118/08/2022

Final Hearing

The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

3
Stage 227/07/2022

Final Hearing

The Tribunal noted the absence of the respondent's counsel due to sanctioned leave and scheduled the appeal for a hearing on 18.08.2022.

4
Stage 313/07/2022

Final Hearing

The Tribunal noted that possession of the flat has been handed to the appellant and ordered the matter to be listed before Bench No. 1 on 27.07.2022 for further hearing.

5
Stage 424/05/2022

Final Hearing

The matter was adjourned due to the reported illness of the learned counsel for the appellant.

6
Stage 521/04/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant due to counsel's illness and rescheduled the hearing for 24.05.2022.

7
Stage 604/03/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for April 21, 2022.

8
Stage 721/01/2022

Final Hearing

No text available.

9
Stage 807/01/2022

Final Hearing

The Tribunal directed the respondent to immediately provide a copy of the conveyance deed to the appellant, noting that while possession has been handed over, the deed was being withheld.

10
Stage 923/12/2021

Final Hearing

The Tribunal adjourned the case to 07.01.2022 and expressed an expectation that the respondent provides habitable possession of the unit and proceeds with the execution of the conveyance deed.

11
Stage 1006/12/2021

Final Hearing

The Tribunal directed the appellant to clear all dues and take possession of the unit following the execution of the conveyance deed, while reserving the issue of interest for delay in possession for the next hearing on 23.12.2021.

12
Stage 1120/11/2021

Final Hearing

No text available.

13
Stage 1208/11/2021

Hearing

The Tribunal granted the respondent a three-week extension to complete finishing work and provide habitable possession of the apartment by 29.11.2021, while noting that the appellant's claim for interest at MCLR+1% will be examined during the final hearing.

14
Stage 1323/10/2021

Hearing

The Tribunal directed the respondent to ensure compliance with its previous order dated 06.09.2021 and scheduled the matter for a status assessment of construction activities on 08.11.2021.

15
Stage 1406/09/2021

Hearing

The Tribunal, expressing shock at the uninhabitable condition of the apartment described in the Advocate Commissioner's report, granted the respondent 60 days to complete construction and make the unit habitable.

16
Stage 1522/01/2021

Hearing

No text available.

17
Stage 1615/12/2020

For Order

No text available.

18
Stage 17Final Ruling Order

Tribunal Order #0901126003072019-18-08-2022

The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

19
Stage 18Interim Order

Tribunal Order #0901126003072019-23-12-2021

The Tribunal adjourned the case to 07.01.2022 and expressed an expectation that the respondent provides habitable possession of the unit and proceeds with the execution of the conveyance deed.

20
Stage 19Interim Order

Tribunal Order #0901126003072019-06-12-2021

The Tribunal directed the appellant to clear all dues and take possession of the unit following the execution of the conveyance deed, while reserving the issue of interest for delay in possession for the next hearing on 23.12.2021.

21
Stage 20Interim Order

Tribunal Order #0901126003072019-08-11-2021

The Tribunal granted the respondent a three-week extension to complete finishing work and provide habitable possession of the apartment by 29.11.2021, while noting that the appellant's claim for interest at MCLR+1% will be examined during the final hearing.

22
Stage 21Interim Order

Tribunal Order #0901126003072019-23-10-2021

The Tribunal directed the respondent to ensure compliance with its previous order dated 06.09.2021 and scheduled the matter for a status assessment of construction activities on 08.11.2021.

23
Stage 22Interim Order

Tribunal Order #0901126003072019-07-01-2022

The Tribunal directed the respondent to immediately provide a copy of the conveyance deed to the appellant, noting that while possession has been handed over, the deed was being withheld.

24
Stage 23Interim Order

Tribunal Order #0901126003072019-06-09-2021

The Tribunal, expressing shock at the uninhabitable condition of the apartment described in the Advocate Commissioner's report, granted the respondent 60 days to complete construction and make the unit habitable.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P. Awarded in favor of Respondent. Awarded interest rate: Rs.5/- per sq. ft. per month.

Disposal Winner: RespondentInterest Rate: Rs.5/- per sq. ft. per monthStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

Ruling Awarded To

Respondent

Awarded Interest Rate

Rs.5/- per sq. ft. per month

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rishi Saxena

Respondent Advocate(s)

  • Rajesh Chadha

Official RERA Tribunal Orders (7)

FINAL_ORDEROrder ID: 0901126003072019-18-08-2022

The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

INTERIM_ORDEROrder ID: 0901126003072019-23-12-2021

The Tribunal adjourned the case to 07.01.2022 and expressed an expectation that the respondent provides habitable possession of the unit and proceeds with the execution of the conveyance deed.

INTERIM_ORDEROrder ID: 0901126003072019-06-12-2021

The Tribunal directed the appellant to clear all dues and take possession of the unit following the execution of the conveyance deed, while reserving the issue of interest for delay in possession for the next hearing on 23.12.2021.

INTERIM_ORDEROrder ID: 0901126003072019-08-11-2021

The Tribunal granted the respondent a three-week extension to complete finishing work and provide habitable possession of the apartment by 29.11.2021, while noting that the appellant's claim for interest at MCLR+1% will be examined during the final hearing.

INTERIM_ORDEROrder ID: 0901126003072019-23-10-2021

The Tribunal directed the respondent to ensure compliance with its previous order dated 06.09.2021 and scheduled the matter for a status assessment of construction activities on 08.11.2021.

INTERIM_ORDEROrder ID: 0901126003072019-07-01-2022

The Tribunal directed the respondent to immediately provide a copy of the conveyance deed to the appellant, noting that while possession has been handed over, the deed was being withheld.

INTERIM_ORDEROrder ID: 0901126003072019-06-09-2021

The Tribunal, expressing shock at the uninhabitable condition of the apartment described in the Advocate Commissioner's report, granted the respondent 60 days to complete construction and make the unit habitable.

TathyaGrid RERA Intelligence AI

Need to research all rulings for parsvnath developers ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →