Appellant / Complainant
Nomani Sadul Haque
Respondent
Parsvnath Developers Ltd.
parsvnath developers ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126003072019 by Nomani Sadul Haque against Parsvnath Developers Ltd. before up_rera.
Final Hearing
The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Final Hearing
The Tribunal noted the absence of the respondent's counsel due to sanctioned leave and scheduled the appeal for a hearing on 18.08.2022.
Final Hearing
The Tribunal noted that possession of the flat has been handed to the appellant and ordered the matter to be listed before Bench No. 1 on 27.07.2022 for further hearing.
Final Hearing
The matter was adjourned due to the reported illness of the learned counsel for the appellant.
Final Hearing
The Tribunal granted an adjournment requested by the appellant due to counsel's illness and rescheduled the hearing for 24.05.2022.
Final Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for April 21, 2022.
Final Hearing
The Tribunal directed the respondent to immediately provide a copy of the conveyance deed to the appellant, noting that while possession has been handed over, the deed was being withheld.
Final Hearing
The Tribunal adjourned the case to 07.01.2022 and expressed an expectation that the respondent provides habitable possession of the unit and proceeds with the execution of the conveyance deed.
Final Hearing
The Tribunal directed the appellant to clear all dues and take possession of the unit following the execution of the conveyance deed, while reserving the issue of interest for delay in possession for the next hearing on 23.12.2021.
Hearing
The Tribunal granted the respondent a three-week extension to complete finishing work and provide habitable possession of the apartment by 29.11.2021, while noting that the appellant's claim for interest at MCLR+1% will be examined during the final hearing.
Hearing
The Tribunal directed the respondent to ensure compliance with its previous order dated 06.09.2021 and scheduled the matter for a status assessment of construction activities on 08.11.2021.
Hearing
The Tribunal, expressing shock at the uninhabitable condition of the apartment described in the Advocate Commissioner's report, granted the respondent 60 days to complete construction and make the unit habitable.
Tribunal Order #0901126003072019-18-08-2022
The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Tribunal Order #0901126003072019-23-12-2021
The Tribunal adjourned the case to 07.01.2022 and expressed an expectation that the respondent provides habitable possession of the unit and proceeds with the execution of the conveyance deed.
Tribunal Order #0901126003072019-06-12-2021
The Tribunal directed the appellant to clear all dues and take possession of the unit following the execution of the conveyance deed, while reserving the issue of interest for delay in possession for the next hearing on 23.12.2021.
Tribunal Order #0901126003072019-08-11-2021
The Tribunal granted the respondent a three-week extension to complete finishing work and provide habitable possession of the apartment by 29.11.2021, while noting that the appellant's claim for interest at MCLR+1% will be examined during the final hearing.
Tribunal Order #0901126003072019-23-10-2021
The Tribunal directed the respondent to ensure compliance with its previous order dated 06.09.2021 and scheduled the matter for a status assessment of construction activities on 08.11.2021.
Tribunal Order #0901126003072019-07-01-2022
The Tribunal directed the respondent to immediately provide a copy of the conveyance deed to the appellant, noting that while possession has been handed over, the deed was being withheld.
Tribunal Order #0901126003072019-06-09-2021
The Tribunal, expressing shock at the uninhabitable condition of the apartment described in the Advocate Commissioner's report, granted the respondent 60 days to complete construction and make the unit habitable.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P. Awarded in favor of Respondent. Awarded interest rate: Rs.5/- per sq. ft. per month.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
Ruling Awarded To
Respondent
Awarded Interest Rate
Rs.5/- per sq. ft. per month
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rishi Saxena
Respondent Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (7)
The Tribunal dismissed the appeal on the grounds that the project is not registered with RERA, rendering the complaint and appeal non-maintainable under the precedent set in M/S Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.
The Tribunal adjourned the case to 07.01.2022 and expressed an expectation that the respondent provides habitable possession of the unit and proceeds with the execution of the conveyance deed.
The Tribunal directed the appellant to clear all dues and take possession of the unit following the execution of the conveyance deed, while reserving the issue of interest for delay in possession for the next hearing on 23.12.2021.
The Tribunal granted the respondent a three-week extension to complete finishing work and provide habitable possession of the apartment by 29.11.2021, while noting that the appellant's claim for interest at MCLR+1% will be examined during the final hearing.
The Tribunal directed the respondent to ensure compliance with its previous order dated 06.09.2021 and scheduled the matter for a status assessment of construction activities on 08.11.2021.
The Tribunal directed the respondent to immediately provide a copy of the conveyance deed to the appellant, noting that while possession has been handed over, the deed was being withheld.
The Tribunal, expressing shock at the uninhabitable condition of the apartment described in the Advocate Commissioner's report, granted the respondent 60 days to complete construction and make the unit habitable.
Need to research all rulings for parsvnath developers ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.