up_reraStatus: Completed
CASE ID: 0901126003062019

Appellant / Complainant

Akhilesh Saran Srivastava

VS

Respondent

U.P. Avas Evam Vikas Parishad

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003062019 by Akhilesh Saran Srivastava against U.P. Avas Evam Vikas Parishad before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 129/09/2022

for delivery of Judgment/Order

The Tribunal set aside the Adjudicating Officer's order and directed the respondent to pay delay interest at the rate of SBI's MCLR+1% per annum from the date of the third allotment (12.04.2017) until the delivery of possession (05.07.2018).

3
Stage 218/07/2022

Re-Hearing

The Tribunal heard arguments from both parties regarding the appellant's submission of documents related to losses suffered, and subsequently reserved the judgment.

4
Stage 305/07/2022

Re-Hearing

The Tribunal directed the respondent to clarify how the appellant can be deemed a defaulter when the final demand and conveyance deed were executed on the same day, and ordered the appellant to submit evidence regarding losses suffered.

5
Stage 419/05/2022

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for July 5, 2022.

6
Stage 505/10/2021

Hearing

The Tribunal heard arguments from both parties regarding Appeal-337/2019 and has reserved the judgment for further consideration.

7
Stage 628/09/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the matter for a final hearing on 05.10.2021, noting that no further adjournments will be permitted.

8
Stage 715/04/2021

Hearing

No text available.

9
Stage 826/03/2021

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and scheduled the appeal for hearing on 15.04.2021.

10
Stage 905/03/2021

Hearing

The appeal is adjourned to 26.03.2021 because lawyers are abstaining from judicial work in support of a call by the Oudh Bar Association.

11
Stage 1024/02/2021

For Order

The appeal is adjourned due to a lawyers' strike called by the Oudh Bar Association and is rescheduled for hearing on 05.03.2021.

12
Stage 1103/02/2021

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 24.02.2021.

13
Stage 1212/01/2021

Final Hearing

No text available.

14
Stage 1310/12/2020

Final Hearing

No text available.

15
Stage 14Final Ruling Order

Tribunal Order #0901126003062019-29-09-2022

The Tribunal set aside the Adjudicating Officer's order and directed the respondent to pay delay interest at the rate of SBI's MCLR+1% per annum from the date of the third allotment (12.04.2017) until the delivery of possession (05.07.2018).

16
Stage 15Interim Order

Tribunal Order #0901126003062019-05-07-2022

The Tribunal directed the respondent to clarify how the appellant can be deemed a defaulter when the final demand and conveyance deed were executed on the same day, and ordered the appellant to submit evidence regarding losses suffered.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order and directed the respondent to pay delay interest at the rate of SBI's MCLR+1% per annum from the date of the third allotment (12.04.2017) until the delivery of possession (05.07.2018). Awarded in favor of Partial. Awarded interest rate: SBI's MCLR+1% per annum.

Disposal Winner: PartialInterest Rate: SBI's MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order and directed the respondent to pay delay interest at the rate of SBI's MCLR+1% per annum from the date of the third allotment (12.04.2017) until the delivery of possession (05.07.2018).

Ruling Awarded To

Partial

Awarded Interest Rate

SBI's MCLR+1% per annum

Interest Period

from 12.04.2017 till 05.07.2018

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Inderpreet Singh Chaddha

Respondent Advocate(s)

  • N N Pandey

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126003062019-29-09-2022

The Tribunal set aside the Adjudicating Officer's order and directed the respondent to pay delay interest at the rate of SBI's MCLR+1% per annum from the date of the third allotment (12.04.2017) until the delivery of possession (05.07.2018).

INTERIM_ORDEROrder ID: 0901126003062019-05-07-2022

The Tribunal directed the respondent to clarify how the appellant can be deemed a defaulter when the final demand and conveyance deed were executed on the same day, and ordered the appellant to submit evidence regarding losses suffered.