Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Laxmi Kant Azad
₹5,41,001
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126002832020 by Greater Noida Industrial Development Authority against Laxmi Kant Azad before up_rera.
Hearing
The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on February 29, 2024.
Hearing
The Tribunal has scheduled the hearing for Appeal-282/2020 to be listed on 24.07.2023.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the matter for hearing on 18.07.2023, to be heard alongside a related appeal.
For Order
The proceedings for Appeal-282/2020 were adjourned due to a request from the appellant's counsel citing health reasons, with the matter rescheduled for 23.05.2023.
For Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for April 17, 2023.
For Order
The Tribunal granted an adjournment of the appeal due to the hospitalization of the appellant's counsel and rescheduled the hearing for March 2, 2023.
For Order
The Tribunal granted a joint request from the counsels of both parties to adjourn the appeal and rescheduled the hearing for 30.01.2023.
For Order
The Tribunal granted an adjournment application filed by the applicant's counsel and rescheduled the case for hearing on 20.12.2022.
For Order
The Tribunal directed the registry to upload a previously unposted order dated 29.09.2022 and instructed the respondent to file a reply to the grounds of appeal before the next hearing on 25.11.2022.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits.
Delay condonation
The Tribunal heard arguments regarding a limitation application and reserved its judgment, while allowing the respondent to submit written arguments by 16.12.2021.
Delay condonation
The Tribunal allowed an application for adjournment and rescheduled the case to 24.11.2021 for the disposal of a limitation application and objections.
Delay condonation
The Tribunal adjourned the case to 26.10.2021 and directed the parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.
Delay condonation
The Tribunal granted an adjournment requested by the counsel for the appellant due to a bereavement in the family and rescheduled the case for 12.04.2021.
For Order
The appeal is adjourned due to a lawyer strike by the Oudh Bar Association and is rescheduled for hearing on 16.03.2021.
Delay condonation
The Tribunal granted the appellant 24 hours to file a reply to the respondent's objections and scheduled the matter for February 26, 2021, to consider the application for condonation of delay.
Tribunal Order #0901126002832020-29-09-2022
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits.
Tribunal Order #0901126002832020-29-02-2024
The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits. The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits. The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR + 1%
Interest Period
from 30.01.2017 till offer of possession
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ajay Kumar Gupta
Respondent Advocate(s)
- Nirmit Srivastav
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits.
The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.