CASE ID: 0901126002832020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Laxmi Kant Azad

Disputed Amount

5,41,001

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

27 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002832020 by Greater Noida Industrial Development Authority against Laxmi Kant Azad before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional Misrepresentation
2
Stage 129/02/2024

Hearing

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

3
Stage 222/01/2024

Hearing

The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on February 29, 2024.

4
Stage 318/10/2023

Hearing

No text available.

5
Stage 412/09/2023

Hearing

No text available.

6
Stage 524/07/2023

Hearing

No text available.

7
Stage 618/07/2023

Hearing

The Tribunal has scheduled the hearing for Appeal-282/2020 to be listed on 24.07.2023.

8
Stage 723/05/2023

For Order

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the matter for hearing on 18.07.2023, to be heard alongside a related appeal.

9
Stage 817/04/2023

For Order

The proceedings for Appeal-282/2020 were adjourned due to a request from the appellant's counsel citing health reasons, with the matter rescheduled for 23.05.2023.

10
Stage 902/03/2023

For Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for April 17, 2023.

11
Stage 1030/01/2023

For Order

The Tribunal granted an adjournment of the appeal due to the hospitalization of the appellant's counsel and rescheduled the hearing for March 2, 2023.

12
Stage 1120/12/2022

For Order

The Tribunal granted a joint request from the counsels of both parties to adjourn the appeal and rescheduled the hearing for 30.01.2023.

13
Stage 1225/11/2022

For Order

The Tribunal granted an adjournment application filed by the applicant's counsel and rescheduled the case for hearing on 20.12.2022.

14
Stage 1320/10/2022

For Order

The Tribunal directed the registry to upload a previously unposted order dated 29.09.2022 and instructed the respondent to file a reply to the grounds of appeal before the next hearing on 25.11.2022.

15
Stage 1429/09/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits.

16
Stage 1524/11/2021

Delay condonation

The Tribunal heard arguments regarding a limitation application and reserved its judgment, while allowing the respondent to submit written arguments by 16.12.2021.

17
Stage 1626/10/2021

Delay condonation

The Tribunal allowed an application for adjournment and rescheduled the case to 24.11.2021 for the disposal of a limitation application and objections.

18
Stage 1724/09/2021

Delay condonation

The Tribunal adjourned the case to 26.10.2021 and directed the parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.

19
Stage 1812/04/2021

Delay condonation

No text available.

20
Stage 1916/03/2021

Delay condonation

The Tribunal granted an adjournment requested by the counsel for the appellant due to a bereavement in the family and rescheduled the case for 12.04.2021.

21
Stage 2026/02/2021

For Order

The appeal is adjourned due to a lawyer strike by the Oudh Bar Association and is rescheduled for hearing on 16.03.2021.

22
Stage 2129/01/2021

Delay condonation

The Tribunal granted the appellant 24 hours to file a reply to the respondent's objections and scheduled the matter for February 26, 2021, to consider the application for condonation of delay.

23
Stage 2206/01/2021

Notice

No text available.

24
Stage 2322/10/2020

Notice

No text available.

25
Stage 24Final Ruling Order

Tribunal Order #0901126002832020-29-09-2022

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits.

26
Stage 25Final Ruling Order

Tribunal Order #0901126002832020-29-02-2024

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits. The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits. The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from 30.01.2017 till offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ajay Kumar Gupta

Respondent Advocate(s)

  • Nirmit Srivastav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126002832020-29-09-2022

The U.P. Real Estate Appellate Tribunal allowed the appellant's application for condonation of delay, subject to a cost of Rs. 12,000, and ordered the defective appeals to be registered as regular appeals for hearing on merits.

FINAL_ORDEROrder ID: 0901126002832020-29-02-2024

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the Regulatory Authority's order to provide possession and pay interest (MCLR+1%) for project delay, and directed the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.