up_reraStatus: Completed
CASE ID: 0901126002772019

Appellant / Complainant

Ashish Verma, Sandy Kundra Verma

VS

Respondent

Sunworld Residency Pvt Ltd

Developer Firm

sunworld residency pvt ltd

Disputed Amount

21,89,074

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002772019 by Ashish Verma, Sandy Kundra Verma against Sunworld Residency Pvt Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 121/03/2022

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and directed the respondent to honor the buy-back clause of the Supplementary Agreement, settle the appellants' HDFC loan, and reimburse all EMIs paid by the appellants.

3
Stage 220/11/2021

Final Hearing

The Tribunal decided to proceed with the hearing of the appeal based on existing records because the respondent failed to provide instructions to their counsel despite being notified of previous orders and the uploaded proceedings.

4
Stage 315/11/2021

Final Hearing

The Tribunal decided to proceed ex-parte against the respondent due to their failure to provide instructions or appear despite multiple communications, and scheduled the matter for hearing on 20.11.2021 based on existing records.

5
Stage 428/10/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 15.11.2021.

6
Stage 501/10/2021

Hearing

The Tribunal decided to proceed ex parte against the respondent due to their repeated absence and lack of representation, scheduling an ex parte hearing for 28.10.2021.

7
Stage 613/09/2021

Hearing

The Tribunal adjourned the appeal to 01.10.2021 as it was the first listing following the lifting of the lockdown and the respondent was not present.

8
Stage 729/04/2021

Hearing

No text available.

9
Stage 806/04/2021

Hearing

No text available.

10
Stage 924/03/2021

Hearing

Due to the absence of the respondent, the Tribunal has adjourned the appeal and rescheduled the hearing for 06.04.2021.

11
Stage 1003/03/2021

Further Consideration

The Tribunal adjourned the appeal to 24.03.2021 and directed the parties to exchange pleadings in the interim.

12
Stage 1115/02/2021

For Order

The Tribunal adjourned the matter due to the absence of the respondent's counsel and rescheduled the hearing for March 3, 2021.

13
Stage 1221/01/2021

Arguments

The Tribunal granted the appellant three days to amend the memo of appeal and established a procedural timeline for the exchange of amended documents, objections, and replies via email and the e-portal.

14
Stage 1312/12/2020

Arguments

No text available.

15
Stage 14Interim Order

Tribunal Order #0901126002772019-20-11-2021

The Tribunal decided to proceed with the hearing of the appeal based on existing records because the respondent failed to provide instructions to their counsel despite being notified of previous orders and the uploaded proceedings.

16
Stage 15Final Ruling Order

Tribunal Order #0901126002772019-21-03-2022

The Tribunal set aside the Regulatory Authority's order and directed the respondent to honor the buy-back clause of the Supplementary Agreement, settle the appellants' HDFC loan, and reimburse all EMIs paid by the appellants.

17
Stage 16Interim Order

Tribunal Order #0901126002772019-15-11-2021

The Tribunal decided to proceed ex-parte against the respondent due to their failure to provide instructions or appear despite multiple communications, and scheduled the matter for hearing on 20.11.2021 based on existing records.

18
Stage 17Interim Order

Tribunal Order #0901126002772019-01-10-2021

The Tribunal decided to proceed ex parte against the respondent due to their repeated absence and lack of representation, scheduling an ex parte hearing for 28.10.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed the respondent to honor the buy-back clause of the Supplementary Agreement, settle the appellants' HDFC loan, and reimburse all EMIs paid by the appellants. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1 percent.

Disposal Winner: AppellantInterest Rate: MCLR + 1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed the respondent to honor the buy-back clause of the Supplementary Agreement, settle the appellants' HDFC loan, and reimburse all EMIs paid by the appellants.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1 percent

Interest Period

from the date of deposit till the date of actual payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Suchita Singh

Respondent Advocate(s)

  • Vipul Gupta

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126002772019-20-11-2021

The Tribunal decided to proceed with the hearing of the appeal based on existing records because the respondent failed to provide instructions to their counsel despite being notified of previous orders and the uploaded proceedings.

FINAL_ORDEROrder ID: 0901126002772019-21-03-2022

The Tribunal set aside the Regulatory Authority's order and directed the respondent to honor the buy-back clause of the Supplementary Agreement, settle the appellants' HDFC loan, and reimburse all EMIs paid by the appellants.

INTERIM_ORDEROrder ID: 0901126002772019-15-11-2021

The Tribunal decided to proceed ex-parte against the respondent due to their failure to provide instructions or appear despite multiple communications, and scheduled the matter for hearing on 20.11.2021 based on existing records.

INTERIM_ORDEROrder ID: 0901126002772019-01-10-2021

The Tribunal decided to proceed ex parte against the respondent due to their repeated absence and lack of representation, scheduling an ex parte hearing for 28.10.2021.

TathyaGrid RERA Intelligence AI

Need to research all rulings for sunworld residency pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →